Metcalf & Eddy Engineering Study Enters Ninth Month With $27,000 in Billings as Board Demands Line-Item Budget Over Project Presentation

NORWOOD – Norwood Planning Board Chairman Thomas F. Cavanaugh voiced sharp frustration on Monday night, November 21, 1977, over mounting delays and rising engineering bills on the town’s feasibility study for the former Norwood Arena land, declaring he was “totally disgusted” with the entire project—and warning, “if I see the plans again, I’m going to get sick.” Reported in The Patriot Ledger on Tuesday, November 22, 1977, the clash erupted when Metcalf and Eddy Inc. project manager James T. Cassidy appeared before the board to review the study’s budget.

Approved by the Planning Board in February 1977 with an expected completion date of June 1977, the engineering study of the former racetrack site had stretched into its ninth month with $24,016 already billed to the town—and another $3,000 in invoices currently being processed. “We seemed to have gotten no place with this study,” Cavanaugh said, rejecting Cassidy’s general budget overview and insisting instead on a detailed line-item budget.

Cassidy defended the escalating costs by explaining that the Boston engineering firm had attended far more municipal meetings than originally anticipated—billing the town for attendance as well as up to eight hours of preparation ahead of certain sessions. When board members noted that the town was already paying for Cassidy’s attendance at Monday’s session and suggested hearing a project presentation since the line-item budget was delayed, Cavanaugh refused. “Because a presentation isn’t on the agenda,” Cavanaugh replied, “and we have no time for it without cancelling everything else.” The board voted to reconvene with Metcalf and Eddy at its upcoming January meeting (printed in the newspaper as Jan. 9, 1977, referring to Jan. 9, 1978).

1977 Norwood Arena Engineering Study Costs Adjusted to 2026 Dollars

Inflation-adjusted using U.S. Bureau of Labor Statistics CPI data ($1.00 in Nov. 1977 ≈ $5.30 in 2026)

1977 Metcalf & Eddy Engineering Study Billing Item 1977 Amount 2026 Equivalent
Billed to Date (Through Month 9) $24,016 ~$127,285
Additional Pending Invoices in Processing $3,000 ~$15,900
Combined Study Billing Total $27,016 ~$143,185
Norwood Arena Site Today (2026): Located off Route 1 (Boston-Providence Turnpike) near the Walpole line, the former Norwood Arena auto-racing oval—which operated from 1948 to 1972—was eventually redeveloped into the commercial and corporate campus known today as Norwood Commerce Center.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.