Metcalf & Eddy Engineering Study Enters Ninth Month With $27,000 in Billings as Board Demands Line-Item Budget Over Project Presentation
NORWOOD – Norwood Planning Board Chairman Thomas F. Cavanaugh voiced sharp frustration on Monday night, November 21, 1977, over mounting delays and rising engineering bills on the town’s feasibility study for the former Norwood Arena land, declaring he was “totally disgusted” with the entire project—and warning, “if I see the plans again, I’m going to get sick.” Reported in The Patriot Ledger on Tuesday, November 22, 1977, the clash erupted when Metcalf and Eddy Inc. project manager James T. Cassidy appeared before the board to review the study’s budget.
Approved by the Planning Board in February 1977 with an expected completion date of June 1977, the engineering study of the former racetrack site had stretched into its ninth month with $24,016 already billed to the town—and another $3,000 in invoices currently being processed. “We seemed to have gotten no place with this study,” Cavanaugh said, rejecting Cassidy’s general budget overview and insisting instead on a detailed line-item budget.
Cassidy defended the escalating costs by explaining that the Boston engineering firm had attended far more municipal meetings than originally anticipated—billing the town for attendance as well as up to eight hours of preparation ahead of certain sessions. When board members noted that the town was already paying for Cassidy’s attendance at Monday’s session and suggested hearing a project presentation since the line-item budget was delayed, Cavanaugh refused. “Because a presentation isn’t on the agenda,” Cavanaugh replied, “and we have no time for it without cancelling everything else.” The board voted to reconvene with Metcalf and Eddy at its upcoming January meeting (printed in the newspaper as Jan. 9, 1977, referring to Jan. 9, 1978).
1977 Norwood Arena Engineering Study Costs Adjusted to 2026 Dollars
Inflation-adjusted using U.S. Bureau of Labor Statistics CPI data ($1.00 in Nov. 1977 ≈ $5.30 in 2026)
| 1977 Metcalf & Eddy Engineering Study Billing Item | 1977 Amount | 2026 Equivalent |
|---|---|---|
| Billed to Date (Through Month 9) | $24,016 | ~$127,285 |
| Additional Pending Invoices in Processing | $3,000 | ~$15,900 |
| Combined Study Billing Total | $27,016 | ~$143,185 |
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
1923 Planning Board Report-Plan for the Vicinity of Center of the Town

The plan on pages 20 and 21 for the center of Norwood is an integral part of the general plan proposed for the Town as a whole. The development of the center cannot be considered separately from the development of the outlying districts as both regions are structurally a part of one another. In the…
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.