A delegation of angry Alandale Parkway residents confronted the Board of Selectmen last night, demanding to know why street acceptance procedures—designated as a “top priority” a full year prior—remained stalled a decade after developer’s performance bonds were released.
Ten-Year Delay in Street Acceptance and Sidewalk Erosion
Led by resident William McCoy of 61 Alandale Parkway, about a dozen homeowners voiced bitter frustrations regarding deteriorated infrastructure and unfulfilled municipal commitments. McCoy questioned the town’s administrative practice of releasing developer bonds prematurely, noting that bonds for Alandale Parkway were discharged 10 years ago while formal street acceptance remains unfinalized, leaving upkeep entirely to property owners.
“The sidewalks are so gross, I don’t know why we’re paying taxes there anymore,” echoed Vincent Cabana of 73 Alandale Parkway, who also cited alarming safety hazards involving gunfire close to residential properties that police reportedly dismissed as permissible on private land.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
State Approves Traffic Barrier to Block East Cross Street Access from Route 1-August 12, 1988
Following a resident petition led by Joseph Burke and Rep. Gregory Sullivan after a child’s injury, the state approved a barrier blocking Route 1 access to East Cross Street.

-
Norwood Committee Faults T Study-July 9, 1987
Discover the 1987 conflict between the Norwood Parking Committee and the MBTA regarding station parking statistics and the pushback against multi-level parking deck plans at the Norwood Depot.

-
SOfficials Tour Ellis Pond Dam and Meadow Brook Sites-August 22, 1984
State Waterways Director John J. Hannon joined Norwood officials to inspect Ellis Pond Dam and the Meadow Brook watershed, targeting $850,000 in state funds toward critical flood mitigation.

-
Adams-Russell Cable Services Tells Norwood Selectmen Local Cable System is Completed-August 8, 1984
Company Announces Energizing of Public Institutional Loop as Two-Year Rate Freeze Certification Process Approaches NORWOOD — Representatives from Adams-Russell Cable Services informed town selectmen last night that Norwood’s cable television system is officially complete. The declaration marks a critical milestone for both the Waltham-based company and local subscribers, as certification triggers the start of a…

-
$1.5 Million Uptown Washington Street Reconstruction and Traffic Improvement Project Scheduled to Begin by Spring 1982-September 10, 1981
State and local officials outline a $1.5 million Washington Street reconstruction project at a public hearing, targeting spring 1982 construction for traffic and street improvements.

-
Guild School Recreation Center Project & Eliot Field Renovation-August 26, 1980
The Norwood Permanent Building Committee selected six architectural firms to interview for the Guild School renovation project, while Norwood Engineering secured the Eliot Field design contract.

-
Guild School Picked for Civic Center-July 8, 1980
Discover the 1980 decision that transformed the Aaron Guild School into a multi-purpose recreation hub, replacing the former Civic Center sold to Norwood Hospital.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.