State Department of Public Works Chief Engineer Robert McDonagh delivered sobering news to local officials and residents last night, stating that the prospect of constructing a new connector road from Interstate 95 to alleviate severe traffic congestion on Neponset Street is highly remote.
Addressing a neighborhood committee gathered at town hall alongside Town Manager John J. Carroll and Selectman Walter J. Dempsey, McDonagh explained that federal and state financial backing—as well as regulatory approval—should not be expected for the proposed multi-million dollar project.
Technical and Financial Hurdles Highlighted
McDonagh pointed out several insurmountable hurdles facing any new interstate connection:
- Interchange Spacing: The distance between the existing I-95 cloverleaf at Neponset Street and the next interchange south at Coney Street in Walpole is far too short to accommodate an additional on-and-off connection. Introducing another link would violate federal spacing standards designed to prevent dangerous traffic turbulence caused by vehicles entering and exiting too frequently.
- Federal Opposition: Because the federal government funded 90 percent of the interstate’s construction cost, federal authorities will strictly block any initiative that compromises smooth traffic flow on the highway.
- Environmental Obstacles: A connector road linking I-95 to Route 1 (routing toward Vanderbilt Avenue in the Park Place industrial park) would require a massive project estimated between $5 million and $10 million, severely complicated by wetlands and deep peat deposits. McDonagh estimated the multi-year planning and approval process could easily span 12 years or more in stiff competition for scarce state and federal dollars.
Town Officials Express Frustration and Weigh Alternatives
Town Manager Carroll noted that an astounding 24,000 vehicles travel down the two-lane Neponset Street every single day. While opening up the currently dead-end Vanderbilt Avenue within the Park Place industrial park might siphon off an estimated 2,500 morning vehicles or 5,000 cars daily, broader relief remains elusive.
Selectman Walter J. Dempsey, a prime booster of the connector road, voiced deep frustration with state transportation policy: “I think the state Department of Public Works and the governor owe us for what they’ve done to that neighborhood. I’ve been mad at the state DPW for years and I’m still mad.” Dempsey noted that a connector road would primarily benefit truckers and motorists heading to Route 1 businesses in the Factory Mutual area by allowing them to bypass congested traffic signals at Cherrywood Drive, Neponset Street, and Dean Street.
Amid the discussion, local resident Walter Thompson of 791 Neponset Street raised a novel counter-proposal: why not restrict or close specific I-95 off-ramps during peak hours—such as southbound traffic exiting onto Neponset Street toward Norwood Center?
While McDonagh admitted he had never been asked that particular question before, Town Manager Carroll—a former DPW commissioner—noted that closing ramps under specific conditions had precedent on the Southeast Expressway and warranted exploration.
Thompson’s idea, along with other mitigation proposals, will be evaluated as part of an upcoming engineering study that town meeting will be asked to approve next month.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
State Approves Traffic Barrier to Block East Cross Street Access from Route 1-August 12, 1988

Following a resident petition led by Joseph Burke and Rep. Gregory Sullivan after a child’s injury, the state approved a barrier blocking Route 1 access to East Cross Street.
-
Norwood Committee Faults T Study-July 9, 1987

Discover the 1987 conflict between the Norwood Parking Committee and the MBTA regarding station parking statistics and the pushback against multi-level parking deck plans at the Norwood Depot.
-
SOfficials Tour Ellis Pond Dam and Meadow Brook Sites-August 22, 1984

State Waterways Director John J. Hannon joined Norwood officials to inspect Ellis Pond Dam and the Meadow Brook watershed, targeting $850,000 in state funds toward critical flood mitigation.
-
Adams-Russell Cable Services Tells Norwood Selectmen Local Cable System is Completed-August 8, 1984

Company Announces Energizing of Public Institutional Loop as Two-Year Rate Freeze Certification Process Approaches NORWOOD — Representatives from Adams-Russell Cable Services informed town selectmen last night that Norwood’s cable television system is officially complete. The declaration marks a critical milestone for both the Waltham-based company and local subscribers, as certification triggers the start of a…
-
State Official Douses Hopes for New I-95 Connector Road to Relieve Heavy Neponset Street Traffic-October 14, 1983

State transportation officials dash hopes for a multi-million dollar I-95 connector road to ease Neponset Street’s daily 24,000-vehicle traffic volume, citing spacing and environmental hurdles.
-
Closed for Years, Repaved Section of Bond Street Set to Reopen-September 21, 1983

Norwood selectmen order the reopening of a closed, repaved section of Bond Street and review upcoming town meeting warrant proposals for Route 1 reconstruction.
-
$1.5 Million Uptown Washington Street Reconstruction and Traffic Improvement Project Scheduled to Begin by Spring 1982-September 10, 1981

State and local officials outline a $1.5 million Washington Street reconstruction project at a public hearing, targeting spring 1982 construction for traffic and street improvements.
-
Guild School Recreation Center Project & Eliot Field Renovation-August 26, 1980

The Norwood Permanent Building Committee selected six architectural firms to interview for the Guild School renovation project, while Norwood Engineering secured the Eliot Field design contract.