State and municipal leaders converged on Norwood yesterday for an on-site inspection of the Ellis Pond Dam and the Meadow Brook drainage area, paving the way for long-awaited flood-prevention improvements backed by $850,000 in recently secured state funding. John J. Hannon, director of the state Division of Waterways, led the walking tour across the earthen dam controlling Ellis Pond, accompanied by State Representative Gregory Sullivan (D-Norwood), Town Manager John J. Carroll, Board of Selectmen members, and conservation commission representatives.

The dam has remained a critical priority since the U.S. Army Corps of Engineers warned four years prior that the structure might lack the structural integrity to withstand outflow during severe rainstorms. “If the dam were to let go… there could be extensive damage to Walpole Street below,” Town Manager Carroll cautioned. To eliminate that risk, the state allocated $450,000 from the newly approved legislative budget to cover design consultation and reconstruction. Hannon explained that rebuilding the dam will likely involve constructing a new concrete-reinforced earth structure equipped with two concrete sluiceways draining into Hawes Brook, a tributary of the Neponset River. Once final designs are completed and construction bids awarded, physical work could commence within a year and reach completion in eight to nine months.

Meadow Brook Drainage Overhaul Faces Complex, Multi-Year Timeline

While the dam project carries a swift timeline, addressing chronic flooding and sewage backups in the Meadow Brook watershed is a far more complex and costly undertaking. The state has appropriated $400,000 to fund initial engineering consulting studies for Meadow Brook, but a preliminary study by Lexington engineering firm Fay, Spofford and Thorndike estimated total construction costs could soar as high as $4 million.

Hannon noted that the project could take anywhere from three to ten years to finalize, depending on annual state appropriations competing against other regional waterways initiatives. However, he emphasized that Norwood’s project holds high priority: “This is an important project due to the nature of the flooding and the prominence of the town. There are many significant people in the town, which had some bearing [in the appropriations].”

The expansive 933-acre Meadow Brook watershed covers 14 percent of Norwood’s land area—including the town center and heavily developed commercial zones extending from Neponset Street near Dean Street to Prospect Street near the Oldham School. Heavy downpours regularly overwhelm the already burdened sewer system, causing stormwater infiltration and severe sewage backups. During major storms in 1978 and 1979, floodwaters inundated land behind the police station and surged four feet deep inside the station itself, creating what Carroll described as “almost catastrophic problems… in a very short time.”

Proposed engineering solutions for the watershed include constructing water-retention basins—with Keohane’s Field under consideration as a potential site—and expanding the underground concrete conduit that carries Meadow Brook from Pleasant Street toward the police station neighborhood. (Reporting by Paul Karon, The Patriot Ledger).

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Engineers Estimate $532,000 Cost for University Avenue Extension-September 4, 1970

    A four-month overdue engineering study prepared by Boston-based consultants Fay, Spofford & Thorndike Inc. at a cost of $8,000 has placed an estimated price tag of $532,000 on the proposed 2,700-foot extension of University Avenue. The recommended roadway layout will connect the existing portion of University Avenue with Everett Street just before intersecting Route 1,…

  • Norwood Kills Funds For School Addition-June 26, 1969

    Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

    Open ledger titled County Ledger 1969 with budget requests marked 'Budget Cut' and a judge's gavel on a wooden desk
  • Norwood Voters To Consider Lighting Funds-June 26, 1968

    The Finance Commission backs the utility expansion alongside a $163,000 sewer construction article, while the town master plan is deferred.

    Series of tall metal power transmission towers with electrical wires over fields and hills
  • Industrial Commission Welcomes Star Service Hub-June 30, 1967

    Following 50 intensive town meetings to resolve department regulations, developers project the new multi-million square foot industrial hub will lower Norwood’s local tax rate.

  • Ask Town Meeting on Industrial Park-September 7, 1966

    Representatives of the development firm Cabot, Cabot & Forbes (CC&F) urged the Board of Selectmen last night to place an article before an early October special town meeting to pave the way for major infrastructure development at the Norwood Industrial Park. C. Brooks Dodge, representing CC&F, asked the board to initiate town meeting action and…

  • State Traffic Engineers Investigate Missing Stop Sign Reports in Norwood-August 31, 1966

    Local frustration over municipal traffic safety measures came to a head when town officials addressed long-standing delays regarding state approval for stop signs at key intersections. Commenting on the sluggish bureaucratic pace, one local selectman dryly remarked, “It takes an act of God to post a stop sign!” The exasperation stemmed from a nine-month delay…

  • Selectmen Call for Up-to-Date Delinquent Debt Listing-August 26, 1965

    Norwood selectmen called for updated listings of delinquent town service accounts and authorized Dr. Norton Fishman to construct an access road along George Willett Parkway at his own expense.

  • Oldham School Drainage Repairs Scheduled For Completion-June 24, 1964

    Corrective Measures Target Long-Standing Controversy At Elementary Site Corrective measures designed to resolve persisting drainage problems at the Oldham Elementary School are scheduled to be completed by the end of this week. The ongoing drainage difficulties at the new school site had been the subject of a long controversy in discussions of the Oldham School…

  • Parking Proposals in Norwood-July 31, 1963

    The Patriot Ledger’s July 31, 1963 edition brought forth a plethora of news stories that captivated the residents of Norwood and surrounding areas. Among these was the Parking Commission’s meeting with the Board of Selectmen to discuss proposals for acquiring land for parking purposes. This pivotal discussion took place in an executive session, which raised…

  • Winslow Train Station Abolished, Leading to Construction of Subway Hill-This Day In Norwood History- July 17, 1891

    This Day In Norwood History- July 17, 1891-Winslow Train Station Abolished, Leading to Construction of Subway Hill


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.