The proposed September opening of the new Junior High South in Norwood faced significant hurdles on the evening of July 11, 1974, as the building committee struggled to determine whether the facility would be ready for students by the start of the school year. The project, which aimed to end three years of double sessions for junior high pupils—who had been forced to attend the North School following the destruction of the old Junior High South by fire in January 1971—remained stalled by last-minute construction delays. Building Committee Chairman John J. Egan noted that the situation had devolved into a “guessing game,” with the committee weighing the possibilities of a delayed opening, continued double sessions, or partial occupancy of the $4.5 million facility.
According to Superintendent Theodore J. Beaudet, the primary obstacles involved the heating control and electrical systems. While Beaudet expressed optimism that the school could be occupied by the start of the term even if sections like the cafeteria and industrial arts area remained unfinished, he emphasized that completion was contingent upon the delivery of essential materials within the next two weeks. Architect James McGrath reported frustrations in coordinating with the Canton-based subcontractor responsible for the heating units, noting that previous assurances of delivery had been thwarted by the absence of key personnel. “We have no hold on them at all,” McGrath stated, highlighting the lack of control the committee had over the supply chain.
In response to the mounting pressure, the building committee took several corrective actions. They mandated that the construction superintendent be reassigned to the project on a full-time basis, reversing a previous decision to reduce his status to part-time. Furthermore, committee member Richard W. Kief successfully moved to have the architects and the general contractor, Rocheford Construction Co., immediately visit the Canton subcontractor to expedite the delivery of parts. The committee also requested that the architects consult with the state building inspector regarding the feasibility of obtaining a temporary occupancy permit, seeking to distinguish between “mandatory” requirements and flexible building standards.
As the committee scrambled to ensure the school’s opening, secondary issues regarding the site’s development emerged. Recreation Superintendent Robert H. Ivatts complained about the installation of a broken gate near the Hawes Pool area, which had reportedly been damaged by children. Additionally, committee member Ernest G. Paciorkowski raised concerns about the state of the landscaping, noting that ball fields at the rear of the property remained bare and had not been properly seeded. With the opening date fast approaching, the committee remained under intense pressure to navigate these complex logistical snags and fulfill the promise of a functional junior high facility for the town’s students.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Norwood Junior High School Honor Rolls for the Last Term-This Day In Norwood History-July 21, 1997

Celebrating Academic Excellence at Norwood Junior High The academic landscape at Norwood Junior High School was highlighted by a formal recognition of student achievement, as the administration released the latest honor rolls for Grade 7 and Grade 6. These lists, comprised of students who attained HIGH HONORS and HONORS status, served as a public commendation…
-
Norwood High School Revives Latin Classes After Nearly a Decade-September 26, 1994

Norwood High School brings back Latin classes for the first time in nearly a decade, led by young instructor Stephen Olbrys to enthusiastic student enrollment.
-
Norwood Elementary Grades Drive Enrollment Increase-September 2, 1993

School System Reaches 3,565 Total Students Norwood public schools have experienced an overall enrollment increase of 136 students compared to the previous academic year, bringing total district enrollment to 3,565 students, according to an announcement made by Assistant Superintendent Roderick Smith during a school committee meeting. Enrollment Breakdown by Grade Level The surge is heavily…
-
Summer Education Program Helps Students Stay Sharp-August 12, 1992

Federal Chapter 1 funding revived Norwood’s summer remedial education program at the Cleveland School, combining academics with local field trips for 48 students.
-
Norwood Parents Music Association: The Dedicated Power Base Behind the High School Band-October 11, 1991

As the fall marching band season kicks into high gear, Joann Pasquantonio is bracing herself for a grueling schedule of long days. There will be days when she boards a school bus at 4:00 p.m. and doesn’t return home until midnight, utterly exhausted after hours of competitions. The catch? Pasquantonio isn’t in the band. She…
-
Prescott Elementary School Parents Urge School Committee to Alleviate Overcrowding-September 12, 1991

Prescott Elementary School parents petition the Norwood School Committee to hire a part-time teacher to alleviate overcrowded kindergarten classes.
-
Schools Open with Retained Programs Despite Budget Cuts and Staff Reductions-September 3, 1991

When Norwood students return to classrooms tomorrow for the start of the new academic year, they will encounter a few visible adjustments—including higher cafeteria prices, a smaller teaching staff, and the discontinuation of Latin courses. However, school officials emphasized that despite a roughly $600,000 reduction to the $18 million school budget amid town-wide cutbacks, Norwood…
-
Search for Superintendent Stirs Conflict on Committee-July 24, 1991

The Norwood School Committee engaged in a tense debate over expanding the superintendent search committee to include PTA representation and broader community voices.
-
Norwood High School to Drop Latin Program Due to Dwindling Enrollment-September 27, 1990

Citing dwindling enrollment and a lack of cost-effectiveness, Norwood High School officials announce that Latin courses will be eliminated from the curriculum after June.
-
Joseph Katchpole Succeeds George Usevich as Vice Principal of Norwood High School-August 23, 1990

Health and physical education department head Joseph Katchpole has been named acting vice principal of Norwood High School, succeeding George Usevich in the school administration.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.