The proposed September opening of the new Junior High South in Norwood faced significant hurdles on the evening of July 11, 1974, as the building committee struggled to determine whether the facility would be ready for students by the start of the school year. The project, which aimed to end three years of double sessions for junior high pupils—who had been forced to attend the North School following the destruction of the old Junior High South by fire in January 1971—remained stalled by last-minute construction delays. Building Committee Chairman John J. Egan noted that the situation had devolved into a “guessing game,” with the committee weighing the possibilities of a delayed opening, continued double sessions, or partial occupancy of the $4.5 million facility.

According to Superintendent Theodore J. Beaudet, the primary obstacles involved the heating control and electrical systems. While Beaudet expressed optimism that the school could be occupied by the start of the term even if sections like the cafeteria and industrial arts area remained unfinished, he emphasized that completion was contingent upon the delivery of essential materials within the next two weeks. Architect James McGrath reported frustrations in coordinating with the Canton-based subcontractor responsible for the heating units, noting that previous assurances of delivery had been thwarted by the absence of key personnel. “We have no hold on them at all,” McGrath stated, highlighting the lack of control the committee had over the supply chain.

In response to the mounting pressure, the building committee took several corrective actions. They mandated that the construction superintendent be reassigned to the project on a full-time basis, reversing a previous decision to reduce his status to part-time. Furthermore, committee member Richard W. Kief successfully moved to have the architects and the general contractor, Rocheford Construction Co., immediately visit the Canton subcontractor to expedite the delivery of parts. The committee also requested that the architects consult with the state building inspector regarding the feasibility of obtaining a temporary occupancy permit, seeking to distinguish between “mandatory” requirements and flexible building standards.

As the committee scrambled to ensure the school’s opening, secondary issues regarding the site’s development emerged. Recreation Superintendent Robert H. Ivatts complained about the installation of a broken gate near the Hawes Pool area, which had reportedly been damaged by children. Additionally, committee member Ernest G. Paciorkowski raised concerns about the state of the landscaping, noting that ball fields at the rear of the property remained bare and had not been properly seeded. With the opening date fast approaching, the committee remained under intense pressure to navigate these complex logistical snags and fulfill the promise of a functional junior high facility for the town’s students.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood School Committee Votes Eliminate Youth Hangout-July 31, 1981

    Following rampant vandalism, late-night drinking, and brush fires near Callahan Elementary School, the Norwood School Committee voted to fund a $6,000 clearing project to eliminate a notorious youth hangout.

  • School Committee Awards New Transportation Contracts-July 16, 1981

    After a difficult budget cycle in 1980, the committee avoided controversy by budgeting accurately and selecting trusted local transportation providers.

  • Henry O. Peabody School Director Ruth Shea Ponders Retirement After 14 Years-August 12, 1980

    After 14 years expanding vocational education, Henry O. Peabody School director Ruth Shea ponders retirement while securing a 97 percent graduate job placement rate.

  • Norwood School Administration Relocates to Willett School-July 24, 1980

    The Norwood School Administration relocated to the George F. Willett School and enacted strict new graduation credit requirements.

  • Students to Face Stiffer Standards-July 18, 1990

    In 1990 the town of Norwood was on the cusp of a significant change in its educational system. The school administration, led by Superintendent Louis J. Taris, had been studying ways to improve academic standards for over a year and a half. The result of this study was a proposal to double the number of…

  • Aaron Guild School Leased to Norwood CETA Consortium and EdCo for One Year-August 1, 1979

    Norwood selectmen voted unanimously to lease the closed Aaron Guild School for one year to the Norwood CETA Consortium and the Educational Collaborative of Greater Boston (EdCo) for $148,000.

  • Norwood School Bus Billing Questioned-July 31, 1979

    The Patriot Ledger’s July 31, 1979 edition brought to light a controversy surrounding the billing practices of Kiessling School Transportation of Dedham, which had been contracted by the town of Norwood to transport special needs children. The issue at hand was whether the company had overcharged the town for mileage on certain routes. According to…

  • Norwood School Committee Considers Staggered School Closing Plan-July 14, 1978

    The school housing needs committee last night recommended a second school closing plan that would close the doors of the Callahan School in September, shut down the Balch School in 1981 and close a third, unnamed elementary school in 1983. The plan was backed by seven of the nine members voting and was billed as…

  • Norwood High School Accessibility Concerns-July 10, 1978

    On July 10, 1978, parents of handicapped students in Norwood voiced serious concerns regarding the lack of physical accessibility at the local high school. Mrs. Charlotte Haskell, president of the Norwood Special Needs Parents Group, recently sent a formal letter to School Superintendent Philip O. Coakley. In the communication, she urged the district to take…

  • School Board Recall Urged-July 8, 1978

    Discover the 1978 budget battle in Norwood, where deep cuts to the school district’s $11.3 million budget led to a controversial recall effort and a lawsuit involving the Massachusetts Teachers Association.


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.