Architect Refuses to Accept 1,100 Square Feet of Exterior Tile at Special Meeting Addressing 22 Construction Issues

Several eleventh-hour construction and administrative hurdles were tackled by the Oldham School Building Committee during a special meeting called last night, headlined by a major dispute over defective masonry. Of prime importance among a list of 22 agenda items was a contentious problem involving the removal of roughly 1,100 square feet of exterior tile. Architect George H. Stoner advised the committee that he formally refused to accept the tile work, characterizing the installation as “poor workmanship.” Stoner explained that the root of the issue stemmed from the wall surface being improperly prepared before the tiles were laid, violating protocol since the tile firm was instructed never to proceed unless the foundation was in acceptable condition.
Prime contractor Edward Goverman Jr. of Canton stated he would be willing to tear down the flawed tiles himself, but noted that a professional tile setter would be required to redo the installation. However, union complications threatened to stall remediation; Goverman warned that because the original subcontractor was unionized, other union personnel currently working on the school might refuse to touch the repair job until all ongoing phases of construction are completed. Architect Stoner warned that the standoff could potentially trigger legal action between the prime contractor and the tile subcontractor, noting that he had requested industry experts to inspect the site. The Building Committee declined to dictate a solution to the contractor, demanding an immediate fix while expressing uncertainty over whether the extensive repairs could be wrapped up before the school’s September opening.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
School Wiring Hazard Suspected at Norwood Junior High-September 3, 1965

Expressing deep concern over aging infrastructure, the Norwood School Committee has called for an immediate investigation into potential electrical wiring hazards at the Norwood Junior High School to determine whether emergency repairs are urgently required. The inquiry was initiated after Superintendent of Schools Philip O. Coakley delivered an alarming report on the condition of the…
-
Norwood Tennis Courts Recreation-July 10, 1965

On July 10, 1965, Norwood officials were actively working to resolve the placement of a proposed six-court tennis facility at the Prescott School. Recreation Superintendent Richard Ready noted that while the specific site remained undecided, he and other town officials were in the process of analyzing a location proposed by the Norwood School Committee. ⠀…
-
Balch School $300,000 Addition Outlines Three Formal State Approval Steps-November 7, 1964

Building Committee Chairman Alec Abdallah detailed the three formal state and municipal steps required to advance the $300,000 Balch School addition, which will add three classrooms, an auditorium, and a cafeteria.
-
Town Meeting Approves Balch and Cleveland School Additions-October 23, 1964

Norwood voters overwhelmingly approved additions for the Balch and Cleveland schools during a town meeting session that also addressed Morrill Memorial Library plans and Plimpton Press electrical upgrades.
-
Norwood Renews Search For High School Principal-June 25, 1964

Officials plan to evaluate past candidates and request recommendations from Boston area colleges while Vice Principal John Mombouquette prepares for interim leadership.
-
Caroline Stratton Breaks Decades-Long Tradition as Female Freshman Class President-October 14, 1963

In a historic student election at Norwood Senior High School, Caroline Stratton becomes the first female freshman class president in over three decades.
-
Enrollment Hike Forces Split Classes in Norwood Public Schools-September 5, 1963

Norwood public schools experience an enrollment spike of 416 students, prompting split classes at Cleveland and Callahan schools and sparking a debate over elementary cafeteria capacity.
-
Eleventh-Hour Decision on Oldham School Registration-September 3, 1963

NORWOOD — An eleventh-hour session of the Oldham School Building Committee is being held tonight to make the decisive call on whether the newly constructed school will officially open its doors for student registration tomorrow morning. Final Scramble and Boiler Inspections Workmen labored through the weekend, including a full day on Saturday, trying to wrap…
-
Oldham School Opening Set for Wednesday, New Teacher Appointments-August 30, 1963

As Norwood prepares for the new academic year, the School Committee has announced plans to open the newly constructed John P. Oldham Elementary School next Wednesday, contingent upon final safety inspections of its heating and ventilating systems. While municipal electric light department crews rushed to finish electrical work and boilers were fired for the first…
-
Bios of New Norwood Public School Teachers-August 29, 1963

As the Norwood public school system prepares for the upcoming academic year, officials announced the appointment of 56 new teachers. Biographical profiles for the first 28 incoming educators highlight their educational backgrounds and assignments: High School Appointments Elementary, Junior High, and Special Services Appointments Discover more from Norwood Historical Society Subscribe to get the latest…
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.
