Building Committee Chairman Alec Abdallah Outlines Plans for Three Classrooms, Auditorium, and Cafeteria
Plans for the $300,000 Balch School addition program must pass three formal requirements before actual construction plans can be advanced. Building Committee Chairman Alec Abdallah said the first step would come at next Thursday’s special town meeting, when the assembly will be asked to give the committee the authority to supervise the construction of the addition. The second step, he said, will come later when the plans will be submitted to the Massachusetts School Building Assistance Commission for reimbursement in state aid, which would amount to about $120,000.
The committee will then submit the program to the Massachusetts Emergency Finance Board, which must clear it because it represents a large capital expenditure for the town. Mr. Abdallah said he would be unable to say when the plans would go out on bid. However, he added that the program would be advanced as quickly as possible. The addition will add three classrooms, an auditorium, and a cafeteria to the Balch School facility.
Balch School Addition Overview
Project Scope & Cost
- Estimated Cost: $300,000 project total
- New Facilities: Three classrooms, an auditorium, and a cafeteria
- Committee Leadership: Chairman Alec Abdallah
Three-Step Approval Process
- Step 1: Special town meeting authority for committee supervision
- Step 2: Massachusetts School Building Assistance Commission review (approx. $120,000 state aid)
- Step 3: Massachusetts Emergency Finance Board capital expenditure clearance
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…
-
Norwood Adopts Whitman-Hanson School Prototype Model to Save Time and Money on New High School Construction-September 13, 2008

Norwood attempts to save time and money on its new high school construction project by reusing the architectural blueprints of Whitman-Hanson Regional High School.
-
Norwood High School Renovation Plans Scrapped in Favor of New Building-October 15, 2005

Facing accreditation warnings and failing infrastructure, Norwood’s School Facility Task Force votes overwhelmingly to pursue a new high school building.
-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.
-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985

Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.
-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976

Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.
-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974

Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.