Building Committee Chairman Alec Abdallah Outlines Plans for Three Classrooms, Auditorium, and Cafeteria
Plans for the $300,000 Balch School addition program must pass three formal requirements before actual construction plans can be advanced. Building Committee Chairman Alec Abdallah said the first step would come at next Thursday’s special town meeting, when the assembly will be asked to give the committee the authority to supervise the construction of the addition. The second step, he said, will come later when the plans will be submitted to the Massachusetts School Building Assistance Commission for reimbursement in state aid, which would amount to about $120,000.
The committee will then submit the program to the Massachusetts Emergency Finance Board, which must clear it because it represents a large capital expenditure for the town. Mr. Abdallah said he would be unable to say when the plans would go out on bid. However, he added that the program would be advanced as quickly as possible. The addition will add three classrooms, an auditorium, and a cafeteria to the Balch School facility.
Balch School Addition Overview
Project Scope & Cost
- Estimated Cost: $300,000 project total
- New Facilities: Three classrooms, an auditorium, and a cafeteria
- Committee Leadership: Chairman Alec Abdallah
Three-Step Approval Process
- Step 1: Special town meeting authority for committee supervision
- Step 2: Massachusetts School Building Assistance Commission review (approx. $120,000 state aid)
- Step 3: Massachusetts Emergency Finance Board capital expenditure clearance
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Superintendent Coakley Tells PTA Council That $4 Million in New School Construction Is Mandatory-September 10, 1965

Dr. Philip O. Coakley tells the PTA Council that $4 million in new school construction—including a new elementary and junior high—is mandatory to handle over-capacity enrollment.
-
School Building Committee Votes to Recommend Addition to Cleveland School-August 16, 1963

By a 3-2 vote, Norwood’s Elementary School Building Committee recommended an eight-room addition to the Cleveland School rather than constructing a new facility on Wilson Street.
-
School Committee Considers New School Sites-March 22, 1962

NORWOOD, Mar, 22 -Arthur B. Rodgers, chairman of the School Housing Study Committee which is responsible for the long-range projection of the towns future school needs, has requested information from the School Committee on its plans for new schools. Being considered by the School Committee are the possibilities of the construction of a second junior…
-
Redecorating Of School Interiors Is Recommended-February 9, 1950

Purchase Of Land For New Stands At High School Also Urged By Supt. Lynch Recommendations for the improvement of the present school plant before the town faced with the problem of new construction were advanced by School Superintendent Lincoln D. Lynch, as principal speaker at the February meeting of the Chamber of Commerce Tuesday night…
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.