Construction Committee Resolves Material Shortages

On July 26, 1974, The Patriot Ledger reported that the prospects for opening the new Junior High South on schedule looked increasingly promising following a progress update delivered at the Permanent Building Construction Committee meeting. Just two weeks prior, the targeted September 3 opening date appeared in jeopardy due to severe material shortages and delayed deliveries. However, architect James McGrath announced that a productive meeting with heating subcontractor Barber-Colman Co. of Canton successfully expedited the supply chain, ensuring that six vital temperature-control panels would be completed and shipped to the Endean Park site by August 15.

Architects from the Norwood firm Korslund, LeNormand and Quann, Inc. also consulted with state Department of Public Safety inspector A. Retacca to review the precise criteria required to secure a 90-day temporary occupancy permit—which can be extended for an additional 90 days—allowing students to begin classes on time and finally ending three years of double sessions necessitated by the tragic fire that destroyed the previous junior high facility.

Inspector A. Retacca stressed that student safety remains paramount, outlining mandatory conditions for partial occupancy. Proper ventilation systems, including operational exhaust fans, must be fully functional, and fire and vandal alarm systems must be tested and directly linked to local police and fire stations. Because an ongoing ironworkers’ strike threatened metal supplies, the inspector indicated that temporary wooden hand railings would be acceptable. While full completion of handicapped accessibility features might be waived if no disabled students are expected immediately or if accommodations can be managed on the ground level, the inspector requested a complete roster of any handicapped adults and children utilizing the building.

Furthermore, emergency generators, sprinkler systems, and fire chief sign-offs on carpet flammability reports are mandatory, and unfinished zones—such as the cafeteria, gymnasium, and industrial arts wing—must be strictly partitioned off from active classrooms. Encouraged by the progress report, the building committee also approved a base fencing bid of $33,781 from Reliable Fence Co. to secure the grounds, while reviewing ongoing work at the Aaron Guild Elementary School, where the board authorized a $4,772 payment to general contractor J.W. Praught Co. as construction moves toward a smooth fall opening.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Coakley Middle School Demolition – June 21, 2025

    Lots of work being done on the entrances and exits to the school, as well as the temporary parking that was put in place last year between the rear of the George H Morse house and the school, but no visible demolition of the building itself. School ended on June 18 and they went right…

  • The Winslow School and Beyond

    From the corner of Cedar Street down to Walpole Street is not actually part of Swedeville. The Winslow family had owned the land between Cedar and Walpole Streets – Their property ran along Chapel Street from Cedar Street to Walpole Street, and along Walpole Street to about Laurel Road. They also owned a large parcel…

  • Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

    Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…

  • New Norwood High’s Official Cost Drops $2 Million-July 21, 2009

    Financial Realignment for the High School Construction Project In the wake of complex negotiations and revised estimates, the project to construct the new Norwood High School has undergone a significant budgetary recalibration. The original authorization granted by the Town Meeting in May had set a budget ceiling of $75 million for the ambitious educational project.…

  • High School Students to Relocate to Vacant Junior High School North-August 21, 1985

    Citing extensive construction delays by Anchor Construction Co., Norwood school officials voted to move nearly 950 high school students to Junior High School North for the start of the school year.

  • Norwood Breaks Ground on $5.1 Million, 96-Unit Everett Street Housing Project-August 22, 1981

    Officials used a bulldozer instead of shovels to break ground on the 96-unit Everett Street housing development for seniors and the handicapped, funded by a $5.1 million federal grant.

  • Selectmen Demand Good Faith Deposit for Winslow School Sale-June 13, 1981

    Board Votes 4-1 to Protect Town Interests Against Developer’s Office Condominium Project as blue Law Video Games Approved The Board of Selectmen have voted 4-1 to formally demand an $8,000 cash deposit from the prospective buyers of the former Winslow School to legally bind a proposed $325,500 real estate purchase. Town Counsel Justin C. Barton…

  • Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976

    Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.

  • High School Addition Plan Okayed-June 20, 1974

    Principal Monbouquette details structural upgrades and media center conversions to combat overcrowding.

  • Committee Votes to Reroof Aaron Guild School Ahead of Winter Months-September 8, 1972

    Norwood’s building committee votes to undertake immediate reroofing of the Aaron Guild School, eliminates skylights, and reviews Endean Park school construction and athletic field costs.


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.