Norwood's School Committee deadlocked 3-3 on reopening the Willett School closing debate, lowered school thermostats to 65 degrees, and reviewed three handicapped accessibility options for Norwood High School.
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974
Norwood's Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.
Norwood School Committee Votes to Duplicate Junior High North-July 30, 1971
The Norwood School Committee voted 4-2 to abandon rebuilding fire-damaged Junior High School South, opting instead to duplicate Junior High North on a new site.
Permanent Building Committee Warns of Cost Overruns for New Junior High School as Subcontract Bids Exceed Estimates-October 27, 1967
Subcontract bids for Norwood's new 117,110-sq-ft junior high school totaled $1.14M, prompting building committee members to warn of necessary town meeting budget increases.
State Approves Preliminary Plans for Two New Norwood Schools-November 18, 1966
State school building officials cleared preliminary plans in November 1966 for Norwood's $4 million junior high and elementary school projects, ensuring a 40 percent state reimbursement ahead of a Dec. 8 Special Town Meeting.
School Needs Study Committee Approves Comprehensive Elementary Expansion Plan and Balch School Addition-November 15, 1963
Norwood's School Needs Study Committee approved plans for a 16-room elementary school and a Balch School cafetorium addition, targeting completion by September 1965.