Committee Recommends New 16-Room Elementary School and Balch Cafetorium While Debating Wilson Street Land Acquisition

NORWOOD – Stepping up efforts to address mounting elementary education pressures, the School Needs Study Committee officially approved a comprehensive report outlining proposed facility expansions. Led by Chairman Arthur Rodgers, the committee unanimously cited an urgent demand for additional classrooms, setting a target completion date of September 1965.

While the committee’s formal report left the specific site recommendation blank pending a final consultation between Rodgers and Superintendent of Schools Philip O. Coakley, the group expressed a general preference for a location near the Cleveland School. The architectural firm of Korslund, LeNormand and Quann has already drawn up rough plans and cost estimates for a 16-room elementary structure, with estimated construction costs projected at approximately $195,000.

Wilson Street Site Hurdles and Order of Runeberg Opposition

The Wilson Street site—previously endorsed by Superintendent Coakley and the School Committee as the premier location for a new school—faced a significant roadblock during committee hearings. Representing the Order of Runeberg, Mrs. Arthur R. Balduf firmly stated that her organization is entirely opposed to selling its Wilson Street property, which is adjacent to town-owned playground land. Noting that an appraiser visited the site, Balduf emphasized that the organization “definitely will not sell.”

In addition to the primary elementary proposal, the study committee recommended an 8-room addition to the Cleveland School alongside a major upgrade to the Balch School. The Balch project would introduce a versatile cafetorium capable of feeding 300 students and serving as an assembly hall seating 500, complete with a shower room, teachers’ dining room, and playroom. The committee noted that the Balch addition would qualify for a 40 percent state reimbursement.

Next Steps and Special Town Meeting Considerations

To advance the initiative, Town Counsel Walter J. Gotovich will be asked to draft an appropriate warrant article once Chairman Rodgers and Superintendent Coakley finalize the site recommendation. The committee will then meet with the Finance Commission to review financial aspects ahead of town meeting action.

Although standard town meetings are not scheduled until January, the Regional Vocational School District study committee has been actively pressing selectmen to call a special town meeting in December. If a special session is convened, the elementary school construction articles could be brought forward for immediate voter consideration.

The complete School Needs Study Committee roster includes Chairman Arthur Rodgers, Paul M. Murphy, Grafton Corbett, Mrs. Francis Wisgirda, Mrs. Robert Brown, Joseph W. Wall, John A. Abdallah, Francis X. Sheehan, and Joseph R. Olshan.

WordPress SEO Package

  • Headline: School Needs Study Committee Approves Elementary Expansion Plan and Balch School Cafetorium
  • Excerpt: Norwood’s School Needs Study Committee approved plans for a 16-room elementary school and a Balch School cafetorium addition, targeting completion by September 1965.
  • Categories: Town History, Norwood Public Schools, Municipal Construction, 1960s Education
  • Comma-Separated WordPress Keywords: arthur rodgers, philip o. coakley, walter j. gotovich, mrs. arthur r. balduf, korslund lenormand and quann, balch school norwood, cleveland school norwood, november, november 15, november 15 1963, 1963, 1960s

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.