Bidding “Gone Wild” Pushes Subcontract Low Bids to $1.14 Million
Subcontractor bids for Norwood’s proposed junior high school opened at noon yesterday, revealing cost figures that virtually guarantee the town will have to request additional funding. Representative Frank Quann of architectural firm Korslund, LeNormand and Quann reported to the permanent building committee that low bids across 17 subcontracting categories totaled $1,146,379.
Because subcontracts typically account for approximately 43 percent of total construction expenses, committee member Ernest G. Paciorcowski warned that exceeding the project’s original $2,995,000 appropriation is now inevitable: “Only a miracle will save us from going over our appropriation… It’s a foregone conclusion we’re going to have to ask for more money at the special town meeting.”
Committee Chairman Justin C. Barton cited soaring labor, materials, and contracting costs across the region, observing that “bidding has gone wild.” Quann noted that 71 percent of new public schools built in Massachusetts this year have required supplementary appropriations before completion, adding that statewide school construction costs are set to jump from $25 to $30 per square foot next week for the 117,110-square-foot facility. Quann expressed disappointment that despite sending out over 93 sets of blueprints, relatively few contractors submitted proposals, leaving only one or two bids in several key categories. General bids for the project are due next Thursday, with eight major contractors expected to compete.
List of Low Subcontract Bids Filed
- Pre-cast concrete: Eastern Fireproofing Corp. (Wakefield) – $39,207
- Masonry (lowest unrestricted): Lusalon Inc. (Burlington) – $270,550
- Roofing & flashing: Burgess and Blacher (Boston) – $33,350
- Metal windows: Eastern Sash Engineering Corp. (Warwick, R.I.) – $14,337
- Waterproofing: Western Waterproofing Co. (Boston) – $8,460
- Miscellaneous & ornamental ironwork: Star Steel Corp. (North Grafton) – $26,480
- Lathing & plastering: Pasco Construction Corp. (Chelsea) – $97,490
- Acoustical tile: The Cheviot Corp. (Needham) – $45,364
- Ceramic & quarry tile: Western Tile Co. (Boston) – $50,000
- Terrazzo: De Paoli Mosaic Co. – $6,900
- Resilient floors: Mari and Sons Flooring (Somerville) – $19,874
- Glass & glazing: Empire Plate and Window Glass (Cambridge) – $17,842
- Painting: Johnson Foster Co. (Somerville) – $28,438
- Plumbing: E.C. Kelly (Knowlton) – $171,655
- Heating & ventilating: Harding, Welding and Piping Corp. (Quincy) – $207,217
- Electrical: Hixon Electric Co. (Braintree) – $358,890
- Kitchen equipment: Peters and Co. (Dorchester) – $55,082
Selectmen Align University Avenue Street Numbers with Westwood
In municipal government action, the Board of Selectmen voted to align street addresses on University Avenue in Norwood sequentially with existing address numbers in neighboring Westwood. The ruling follows a formal request by Star Market, which constructed a major warehouse complex within the Norwood Industrial Park along the cross-town thoroughfare.
Local Republican Town Committee Hosts Autumn Dinner-Dance
In community news, the Norwood Republican Town Committee will host a smorgasbord dinner and dance tomorrow evening at the American Legion Hall. Organization committee members Barbara A. Barton (359 Prospect St.), Edith H. Bloom (316 Washington St.), and Ralph B. Hersey Jr. (30 Chatham Rd.) are handling ticket sales for the event, which features cocktails at 6:30 p.m. and live music by Ernie Gotham.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…
-
Norwood Adopts Whitman-Hanson School Prototype Model to Save Time and Money on New High School Construction-September 13, 2008

Norwood attempts to save time and money on its new high school construction project by reusing the architectural blueprints of Whitman-Hanson Regional High School.
-
Norwood High School Renovation Plans Scrapped in Favor of New Building-October 15, 2005

Facing accreditation warnings and failing infrastructure, Norwood’s School Facility Task Force votes overwhelmingly to pursue a new high school building.
-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.
-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985

Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.
-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976

Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.
-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974

Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.