Construction Committee Resolves Material Shortages

On July 26, 1974, The Patriot Ledger reported that the prospects for opening the new Junior High South on schedule looked increasingly promising following a progress update delivered at the Permanent Building Construction Committee meeting. Just two weeks prior, the targeted September 3 opening date appeared in jeopardy due to severe material shortages and delayed deliveries. However, architect James McGrath announced that a productive meeting with heating subcontractor Barber-Colman Co. of Canton successfully expedited the supply chain, ensuring that six vital temperature-control panels would be completed and shipped to the Endean Park site by August 15.
Architects from the Norwood firm Korslund, LeNormand and Quann, Inc. also consulted with state Department of Public Safety inspector A. Retacca to review the precise criteria required to secure a 90-day temporary occupancy permit—which can be extended for an additional 90 days—allowing students to begin classes on time and finally ending three years of double sessions necessitated by the tragic fire that destroyed the previous junior high facility.
Inspector A. Retacca stressed that student safety remains paramount, outlining mandatory conditions for partial occupancy. Proper ventilation systems, including operational exhaust fans, must be fully functional, and fire and vandal alarm systems must be tested and directly linked to local police and fire stations. Because an ongoing ironworkers’ strike threatened metal supplies, the inspector indicated that temporary wooden hand railings would be acceptable. While full completion of handicapped accessibility features might be waived if no disabled students are expected immediately or if accommodations can be managed on the ground level, the inspector requested a complete roster of any handicapped adults and children utilizing the building.
Furthermore, emergency generators, sprinkler systems, and fire chief sign-offs on carpet flammability reports are mandatory, and unfinished zones—such as the cafeteria, gymnasium, and industrial arts wing—must be strictly partitioned off from active classrooms. Encouraged by the progress report, the building committee also approved a base fencing bid of $33,781 from Reliable Fence Co. to secure the grounds, while reviewing ongoing work at the Aaron Guild Elementary School, where the board authorized a $4,772 payment to general contractor J.W. Praught Co. as construction moves toward a smooth fall opening.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976
Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.

-
High School Addition Plan Okayed-June 20, 1974
Principal Monbouquette details structural upgrades and media center conversions to combat overcrowding.

-
Permanent School Building Construction Committee Votes to Proceed with Permanent Roof Plans for Burned-Out Junior High South and Aaron Guild School-September 15, 1972
School building construction committee votes to proceed with permanent roof plans for Junior High South and Aaron Guild School, while Endean Park junior high plans secure SBAB approval.

-
Building Committee Votes to Relocate Endean Park Softball Fields for New Junior High South Project-August 11, 1972
The permanent building committee unanimously voted to relocate and lengthen two softball fields at Endean Park to accommodate the new Junior High South project.⠀

-
Norwood School Committee Votes to Duplicate Junior High North-July 30, 1971
The Norwood School Committee voted 4-2 to abandon rebuilding fire-damaged Junior High School South, opting instead to duplicate Junior High North on a new site.

-
Norwood Junior High School Building Committee Reviews Five Replacement Plans-July 27, 1971
The Norwood building committee reviewed five alternate architectural plans for a new junior high school while exploring federal disaster aid.

-
Officials Weighing School Repair Cost-March 6, 1971
Selectmen last night favored start on work to secure walls of the fire-gutted third story of Norwood Junior High School South which are still standing after a section of the rear wall collapsed Thursday. Architect’s Proposal The local architectural firm of Korslund, LeNormand and Quann, Inc., which directed the construction of the temporary roof damaged…

-
Independent School Survey Recommends $21.8 Million Building Program, Terming Norwood Schools ‘Critically Overcrowded’-September 17, 1970
An independent master plan by Arthur D. Little recommends a $21.8 million building program to combat critical overcrowding across all Norwood school levels.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.