Architect Refuses to Accept 1,100 Square Feet of Exterior Tile at Special Meeting Addressing 22 Construction Issues

Several eleventh-hour construction and administrative hurdles were tackled by the Oldham School Building Committee during a special meeting called last night, headlined by a major dispute over defective masonry. Of prime importance among a list of 22 agenda items was a contentious problem involving the removal of roughly 1,100 square feet of exterior tile. Architect George H. Stoner advised the committee that he formally refused to accept the tile work, characterizing the installation as “poor workmanship.” Stoner explained that the root of the issue stemmed from the wall surface being improperly prepared before the tiles were laid, violating protocol since the tile firm was instructed never to proceed unless the foundation was in acceptable condition.
Prime contractor Edward Goverman Jr. of Canton stated he would be willing to tear down the flawed tiles himself, but noted that a professional tile setter would be required to redo the installation. However, union complications threatened to stall remediation; Goverman warned that because the original subcontractor was unionized, other union personnel currently working on the school might refuse to touch the repair job until all ongoing phases of construction are completed. Architect Stoner warned that the standoff could potentially trigger legal action between the prime contractor and the tile subcontractor, noting that he had requested industry experts to inspect the site. The Building Committee declined to dictate a solution to the contractor, demanding an immediate fix while expressing uncertainty over whether the extensive repairs could be wrapped up before the school’s September opening.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Assistant Superintendent James R. Donovan Ending 43-Year Journey in Norwood School System-November 6, 1980

Marking the end of a 43-year career as a student, teacher, and administrator, Norwood Assistant Superintendent James R. Donovan announced his retirement effective December 31, 1980.
-
Norwood High School Renovation Plans Scrapped in Favor of New Building-October 15, 2005

Facing accreditation warnings and failing infrastructure, Norwood’s School Facility Task Force votes overwhelmingly to pursue a new high school building.
-
Norwood Junior High School Honor Rolls for the Last Term-This Day In Norwood History-July 21, 1997

Celebrating Academic Excellence at Norwood Junior High The academic landscape at Norwood Junior High School was highlighted by a formal recognition of student achievement, as the administration released the latest honor rolls for Grade 7 and Grade 6. These lists, comprised of students who attained HIGH HONORS and HONORS status, served as a public commendation…
-
Norwood High School Revives Latin Classes After Nearly a Decade-September 26, 1994

Norwood High School brings back Latin classes for the first time in nearly a decade, led by young instructor Stephen Olbrys to enthusiastic student enrollment.
-
Norwood Elementary Grades Drive Enrollment Increase-September 2, 1993

School System Reaches 3,565 Total Students Norwood public schools have experienced an overall enrollment increase of 136 students compared to the previous academic year, bringing total district enrollment to 3,565 students, according to an announcement made by Assistant Superintendent Roderick Smith during a school committee meeting. Enrollment Breakdown by Grade Level The surge is heavily…
-
Summer Education Program Helps Students Stay Sharp-August 12, 1992

Federal Chapter 1 funding revived Norwood’s summer remedial education program at the Cleveland School, combining academics with local field trips for 48 students.
-
Norwood Parents Music Association: The Dedicated Power Base Behind the High School Band-October 11, 1991

As the fall marching band season kicks into high gear, Joann Pasquantonio is bracing herself for a grueling schedule of long days. There will be days when she boards a school bus at 4:00 p.m. and doesn’t return home until midnight, utterly exhausted after hours of competitions. The catch? Pasquantonio isn’t in the band. She…
-
Prescott Elementary School Parents Urge School Committee to Alleviate Overcrowding-September 12, 1991

Prescott Elementary School parents petition the Norwood School Committee to hire a part-time teacher to alleviate overcrowded kindergarten classes.
-
Schools Open with Retained Programs Despite Budget Cuts and Staff Reductions-September 3, 1991

When Norwood students return to classrooms tomorrow for the start of the new academic year, they will encounter a few visible adjustments—including higher cafeteria prices, a smaller teaching staff, and the discontinuation of Latin courses. However, school officials emphasized that despite a roughly $600,000 reduction to the $18 million school budget amid town-wide cutbacks, Norwood…
-
Search for Superintendent Stirs Conflict on Committee-July 24, 1991

The Norwood School Committee engaged in a tense debate over expanding the superintendent search committee to include PTA representation and broader community voices.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.