Architect Refuses to Accept 1,100 Square Feet of Exterior Tile at Special Meeting Addressing 22 Construction Issues

Several eleventh-hour construction and administrative hurdles were tackled by the Oldham School Building Committee during a special meeting called last night, headlined by a major dispute over defective masonry. Of prime importance among a list of 22 agenda items was a contentious problem involving the removal of roughly 1,100 square feet of exterior tile. Architect George H. Stoner advised the committee that he formally refused to accept the tile work, characterizing the installation as “poor workmanship.” Stoner explained that the root of the issue stemmed from the wall surface being improperly prepared before the tiles were laid, violating protocol since the tile firm was instructed never to proceed unless the foundation was in acceptable condition.

Prime contractor Edward Goverman Jr. of Canton stated he would be willing to tear down the flawed tiles himself, but noted that a professional tile setter would be required to redo the installation. However, union complications threatened to stall remediation; Goverman warned that because the original subcontractor was unionized, other union personnel currently working on the school might refuse to touch the repair job until all ongoing phases of construction are completed. Architect Stoner warned that the standoff could potentially trigger legal action between the prime contractor and the tile subcontractor, noting that he had requested industry experts to inspect the site. The Building Committee declined to dictate a solution to the contractor, demanding an immediate fix while expressing uncertainty over whether the extensive repairs could be wrapped up before the school’s September opening.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Newcomers Learn to Take Middle School in Their Stride-September 7, 1989

    Transitioning from elementary school to middle school can be an intimidating milestone for any young student, but as classes officially got underway this week, Norwood’s newest middle schoolers quickly learned to take the change in stride. Navigating larger hallways, adjusting to rotating class schedules, and meeting new teachers mark a major rite of passage for…

  • First Day of School Brings Excitement and New Beginnings for Norwood’s Class of 1999-September 10, 1987

    Norwood students return to class for the 1987-88 school year, marking the first day of school for the Balch Elementary first-graders who make up the graduating class of 1999.

  • Balch and Norwood High Welcome Students on the First Day of School for the Class of 1999-September 10, 1987

    Balch Elementary and Norwood High welcome students back for the 1987-88 academic year, marking the first day of school for the graduating Class of 1999.

  • Norwood High Teachers to Implement Uniform Curriculum Guides Starting Next Week-September 3, 1987

    When classes resume next week, high school teachers across Norwood will officially be “going by the book.” Superintendent of Schools James Savage informed the school committee that faculty members teaching every course—from woodshop to algebra—will be required to follow newly established, standardized curriculum guides authored by Norwood educators. Closing the Gap in District Education The…

  • $16,600 Grant Equips New Norwood High School Cable Television Studio-August 18, 1987

    Norwood Community Television awarded a $16,600 grant to equip a new student-run television studio at Norwood High School, expanding local cable programming and production training.

  • Norwood High School Releases Fourth-Quarter Honor Roll-August 14, 1986

    Norwood High School announced its student honor roll for the fourth quarter of the 1985-1986 academic year, recognizing academic achievement across senior, junior, and sophomore classes.

  • Extra $10,000 Approved for High School Renovation-August 7, 1986

    Amid project delays tied to Anchor Construction Corp., the Norwood Finance Commission voted 3-1 to approve an extra $10,000 for KL&Q Architects to oversee the completion of the $5 million high school renovation.

  • School Opening Delayed for High School Students-August 27, 1985

    Norwood high school classes are delayed to September 9 as students temporarily relocate to Junior High North during a $5 million renovation project.

  • High School Students to Relocate to Vacant Junior High School North-August 21, 1985

    Citing extensive construction delays by Anchor Construction Co., Norwood school officials voted to move nearly 950 high school students to Junior High School North for the start of the school year.

  • Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

    Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.