Architect Refuses to Accept 1,100 Square Feet of Exterior Tile at Special Meeting Addressing 22 Construction Issues

Several eleventh-hour construction and administrative hurdles were tackled by the Oldham School Building Committee during a special meeting called last night, headlined by a major dispute over defective masonry. Of prime importance among a list of 22 agenda items was a contentious problem involving the removal of roughly 1,100 square feet of exterior tile. Architect George H. Stoner advised the committee that he formally refused to accept the tile work, characterizing the installation as “poor workmanship.” Stoner explained that the root of the issue stemmed from the wall surface being improperly prepared before the tiles were laid, violating protocol since the tile firm was instructed never to proceed unless the foundation was in acceptable condition.

Prime contractor Edward Goverman Jr. of Canton stated he would be willing to tear down the flawed tiles himself, but noted that a professional tile setter would be required to redo the installation. However, union complications threatened to stall remediation; Goverman warned that because the original subcontractor was unionized, other union personnel currently working on the school might refuse to touch the repair job until all ongoing phases of construction are completed. Architect Stoner warned that the standoff could potentially trigger legal action between the prime contractor and the tile subcontractor, noting that he had requested industry experts to inspect the site. The Building Committee declined to dictate a solution to the contractor, demanding an immediate fix while expressing uncertainty over whether the extensive repairs could be wrapped up before the school’s September opening.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood Rejects Rockland Offer of Part Payment-July 16, 1985

    The summer of 1985 was a time of great economic uncertainty in Massachusetts, with the state facing significant budget deficits and high unemployment rates. However, amidst this backdrop of fiscal woes, the town of Norwood found itself embroiled in a dispute with its neighboring municipality, Rockland, over tuition fees for vocational school students. The issue…

    Stack of papers listing vocational school costs including tuition, equipment, registration, and book fees
  • Norwood High School Implements Total Smoking Ban-July 3, 1985

    In July 1985, the Norwood School Committee unanimously approved a total smoking ban at Norwood High School to begin in September, prioritizing the health of its students.

    Ashtray filled with cigarette butts labeled 'No Smoking' with people drinking and smoking in background
  • Recess is a Popular Subject Among Crop of First Graders-September 6, 1984

    First-grader Amy Frigulietti sat at her desk yesterday, reaching inside to rearrange her freshly sharpened pencils, pens, and a notebook featuring a picture of Michael Jackson on the cover. Like many of her peers across Norwood, 6-year-old Amy was eager for the new term in teacher Sandy Barner‘s class at Prescott Elementary School, though she…

  • Norwood Kindergarten Bus Routes Announced for Fall Term-September 9, 1983

    School officials have officially released the comprehensive morning and afternoon bus route schedules for Norwood kindergarten students, with classes set to begin on Monday. Schedule and School-Specific Route Details The morning kindergarten session commences at 8:40 a.m. (with first pickups beginning at 8:20 a.m. and dismissal at 11:15 a.m.), while the afternoon session begins at…

  • Rain-Damaged Cleveland and Prescott Schools Expected to Be Repaired by September-August 17, 1983

    Unexpected rainstorms caused roof leaks at the Cleveland and Prescott schools during active construction, though officials expect full contractor-funded repairs before the September opening.

  • School Officials Seek $62,700 from Town Meeting to Fund Classroom Computers-September 10, 1982

    School officials plan to ask town meeting for $62,700 to purchase 16 computers for elementary, junior high, and high schools to introduce students to computer technology.

  • Selectmen Target $82,500 for Gymnasium Repairs While Uncovering Wider $750,000 School Roof Crisis-September 9, 1982

    Facing extensive water damage at Norwood High School, selectmen tentatively agreed to recommend an $82,500 appropriation at the September 20 special town meeting—while a broader engineering survey revealed an estimated $750,000 in necessary roof repairs across the school district. Gym Floor Damage and Architectural Estimates An August 9 rainstorm caused severe rainwater leakage from a…

  • John Poce Appointed Acting Principal of Junior High School North-September 9, 1982

    Junior High School North vice-principal John Poce is unanimously appointed acting principal by the school committee following James R. Savage’s promotion to superintendent.

  • Norwood Public School Students Score Strongly on State Basic-Skills Exams-September 2, 1982

    Students across Norwood public schools have demonstrated exceptional academic performance, scoring remarkably well on state-mandated basic-skills tests for the second consecutive year. Released recently following examinations administered last spring, the district data reveals that only a very small handful of students across grades three, five, and eight failed to achieve minimum passing standards in reading,…

  • School Long-Range Planning Panel to Deliver Progress Report-August 24, 1982

    Facing declining enrollments, Norwood’s school planning panel will deliver a progress report in October and final recommendations on grade configurations and potential school closures in January.


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.