The Oldham School Building Committee called an emergency meeting following a stormy session marred by heated clashes and the dramatic walkout of general contractor Edward Goverman. Committee members united in condemning what they termed severe construction deficiencies and poor workmanship at the new Oldham Elementary School, casting serious doubt on whether the facility will be ready to open for the September 4 start of the academic year.
Superintendent of Schools Philip O. Coakley admitted that no alternative plan has been prepared in the event of a delay, noting that the opening is now viewed with “a great deal of apprehension.” Committee member Mrs. Ellen A. Dixon led the criticism against Goverman, citing a cascade of structural grievances including defective exterior tile work, the use of unlabeled paint, roof and window leaks, unground concrete floors, short-cut steel beams with aluminum plate covers, and a failure to clear massive rocks from the landscaping. Frustrated when Mrs. Dixon directed her questions to architect George H. Stoner rather than himself, Goverman declared, “There’s no sense in my sitting here,” and strode out of the meeting room.
Architect Stoner and Clerk of the Works William Snyder conceded that workmanship had fallen short in multiple areas. Snyder noted that the contractor had failed to maintain proper on-site supervision or deploy the skilled labor demanded by project specifications, frequently substituting lower-paid laborers instead. Committee member Ambrose J. Kelly sharply criticized the project as a “patchwork job,” estimating that accepting the building in its current state could force the town to spend $125,000 to $150,000 on repairs within five years, and predicted a 30- to 60-day opening delay. Committee member Arthur B. Rodgers added that he had flagged 32 roof leaks months prior due to improperly installed flashing.
Rather than hire an outside engineering firm as initially proposed by Mrs. Dixon, the committee voted unanimously to summon representatives of the company bonding the construction project, alongside Town Counsel Walter J. Gotovich and architect Stoner, to review legal options, demand accelerated corrective work, and address potential damages. (
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…
-
Norwood Adopts Whitman-Hanson School Prototype Model to Save Time and Money on New High School Construction-September 13, 2008

Norwood attempts to save time and money on its new high school construction project by reusing the architectural blueprints of Whitman-Hanson Regional High School.
-
Norwood High School Renovation Plans Scrapped in Favor of New Building-October 15, 2005

Facing accreditation warnings and failing infrastructure, Norwood’s School Facility Task Force votes overwhelmingly to pursue a new high school building.
-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.
-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985

Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.
-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976

Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.
-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974

Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.