The Oldham School Building Committee called an emergency meeting following a stormy session marred by heated clashes and the dramatic walkout of general contractor Edward Goverman. Committee members united in condemning what they termed severe construction deficiencies and poor workmanship at the new Oldham Elementary School, casting serious doubt on whether the facility will be ready to open for the September 4 start of the academic year.
Superintendent of Schools Philip O. Coakley admitted that no alternative plan has been prepared in the event of a delay, noting that the opening is now viewed with “a great deal of apprehension.” Committee member Mrs. Ellen A. Dixon led the criticism against Goverman, citing a cascade of structural grievances including defective exterior tile work, the use of unlabeled paint, roof and window leaks, unground concrete floors, short-cut steel beams with aluminum plate covers, and a failure to clear massive rocks from the landscaping. Frustrated when Mrs. Dixon directed her questions to architect George H. Stoner rather than himself, Goverman declared, “There’s no sense in my sitting here,” and strode out of the meeting room.
Architect Stoner and Clerk of the Works William Snyder conceded that workmanship had fallen short in multiple areas. Snyder noted that the contractor had failed to maintain proper on-site supervision or deploy the skilled labor demanded by project specifications, frequently substituting lower-paid laborers instead. Committee member Ambrose J. Kelly sharply criticized the project as a “patchwork job,” estimating that accepting the building in its current state could force the town to spend $125,000 to $150,000 on repairs within five years, and predicted a 30- to 60-day opening delay. Committee member Arthur B. Rodgers added that he had flagged 32 roof leaks months prior due to improperly installed flashing.
Rather than hire an outside engineering firm as initially proposed by Mrs. Dixon, the committee voted unanimously to summon representatives of the company bonding the construction project, alongside Town Counsel Walter J. Gotovich and architect Stoner, to review legal options, demand accelerated corrective work, and address potential damages. (
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Superintendent Coakley Tells PTA Council That $4 Million in New School Construction Is Mandatory-September 10, 1965

Dr. Philip O. Coakley tells the PTA Council that $4 million in new school construction—including a new elementary and junior high—is mandatory to handle over-capacity enrollment.
-
School Building Committee Votes to Recommend Addition to Cleveland School-August 16, 1963

By a 3-2 vote, Norwood’s Elementary School Building Committee recommended an eight-room addition to the Cleveland School rather than constructing a new facility on Wilson Street.
-
School Committee Considers New School Sites-March 22, 1962

NORWOOD, Mar, 22 -Arthur B. Rodgers, chairman of the School Housing Study Committee which is responsible for the long-range projection of the towns future school needs, has requested information from the School Committee on its plans for new schools. Being considered by the School Committee are the possibilities of the construction of a second junior…
-
Redecorating Of School Interiors Is Recommended-February 9, 1950

Purchase Of Land For New Stands At High School Also Urged By Supt. Lynch Recommendations for the improvement of the present school plant before the town faced with the problem of new construction were advanced by School Superintendent Lincoln D. Lynch, as principal speaker at the February meeting of the Chamber of Commerce Tuesday night…
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.