The Oldham School Building Committee called an emergency meeting following a stormy session marred by heated clashes and the dramatic walkout of general contractor Edward Goverman. Committee members united in condemning what they termed severe construction deficiencies and poor workmanship at the new Oldham Elementary School, casting serious doubt on whether the facility will be ready to open for the September 4 start of the academic year.

Superintendent of Schools Philip O. Coakley admitted that no alternative plan has been prepared in the event of a delay, noting that the opening is now viewed with “a great deal of apprehension.” Committee member Mrs. Ellen A. Dixon led the criticism against Goverman, citing a cascade of structural grievances including defective exterior tile work, the use of unlabeled paint, roof and window leaks, unground concrete floors, short-cut steel beams with aluminum plate covers, and a failure to clear massive rocks from the landscaping. Frustrated when Mrs. Dixon directed her questions to architect George H. Stoner rather than himself, Goverman declared, “There’s no sense in my sitting here,” and strode out of the meeting room.

Architect Stoner and Clerk of the Works William Snyder conceded that workmanship had fallen short in multiple areas. Snyder noted that the contractor had failed to maintain proper on-site supervision or deploy the skilled labor demanded by project specifications, frequently substituting lower-paid laborers instead. Committee member Ambrose J. Kelly sharply criticized the project as a “patchwork job,” estimating that accepting the building in its current state could force the town to spend $125,000 to $150,000 on repairs within five years, and predicted a 30- to 60-day opening delay. Committee member Arthur B. Rodgers added that he had flagged 32 roof leaks months prior due to improperly installed flashing.

Rather than hire an outside engineering firm as initially proposed by Mrs. Dixon, the committee voted unanimously to summon representatives of the company bonding the construction project, alongside Town Counsel Walter J. Gotovich and architect Stoner, to review legal options, demand accelerated corrective work, and address potential damages. (

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

    Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…

  • Voters Approve New Norwood High School-April 12, 2009

    Norwood High School Project Faces Delay Despite Overwhelming Voter Support On April 12, 2009, Norwood found itself at a dramatic crossroads — one defined by overwhelming civic unity on the one hand, and a sudden, unexpected construction setback on the other. Just days earlier, Norwood residents had delivered one of the most decisive votes in…

  • Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

    Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.

  • Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985

    Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.

  • Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974

    Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.

  • Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

    After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.

  • Unfinished Junior High To Open On Schedule-July 8, 1974

    Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.

  • Gridlock Over $6-Million Junior High Rebuilding Plan and Norwood Arena Noise-This Day in Norwood History-June 27, 1971

    A dual crisis hits Norwood in 1971 as a $6-million junior high deficit triggers political warfare and state experts condemn racetrack noise.

    Teacher writing school budget details on chalkboard with students listening and thinking about funding issues
  • Work Under Way At Junior High North-May 29, 1970

    In 1970, Norwood Junior High North saw new fencing, repaving, and drainage improvements while a major school facilities survey moved toward completion, shaping long‑term planning.

  • Norwood Kills Funds For School Addition-June 26, 1969

    Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

    Open ledger titled County Ledger 1969 with budget requests marked 'Budget Cut' and a judge's gavel on a wooden desk


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.