Board Refuses Bond Releases on Fieldbrook Drive, Dell Road, and Croyden Road and Holds Off on Hampden Road Estimate Pending Utility Inspections
NORWOOD – Frustrated by 17 years of unfinished subdivision roadwork off Chapel Street, members of the Norwood Planning Board engaged in heated debate on Monday night, November 20, 1967, over calling the performance bonds on the long-stalled Albert P. Nelson residential subdivision—refusing to release existing bonds on Fieldbrook Drive, Dell Road, and Croyden Road while signaling they would reject any further requests for extensions. Reported in The Patriot Ledger on Tuesday, November 21, 1967, the dispute centered on lingering infrastructure defects that had prevented the neighborhood streets from meeting Norwood town engineering standards for nearly two decades.
According to Town Engineer Robert A. Hamilton, inspections revealed multiple construction discrepancies along Fieldbrook Drive and Dell Road—which had been built by contractor Frank Simoni—as well as Croyden Road, built by Philip Phillips. The prolonged standoff sparked bitter discussion among board members, who struggled to recall why the town had not called the developer’s surety bonds years earlier. When Hamilton observed that late November was the wrong season for road construction, Planning Board member Francis Wisgirda shot back, “It’s always the wrong time of year,” while member Thomas A. Riolo pointed out that Mr. Nelson “has had 17 summers to complete the roads.”
Calling performance bonds allows the municipality to seize developer-backed insurance funds to finish substandard streets itself, though board members noted that bond forfeitures frequently trigger litigation. Wisgirda formally recommended that the board prepare to call the bonds at its next meeting if Nelson requested additional time—and do so without waiting to notify him in advance. Chairman J. Edward Bamber declared that if the developer sought another extension, the board’s answer would be to finish the streets “before we get to court.”
In separate subdivision bond business the same evening, the Planning Board declined to set a performance bond amount for Hampden Road until installed utilities were cleaned and inspected by Town Engineer Hamilton. The bond estimate request had been submitted by Walpole attorney Bernard J. Martin on behalf of Benjamin Koehl, David Harris, and Robert Green, the current owners of the 23-lot subdivision originally owned by A. C. Riley of Canton, who had installed the initial street utilities. Hamilton advised the board he could not calculate a reliable bond figure until the underground utilities were thoroughly flushed and verified.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Limit Growth on Rte. 1 or Face Freeze, Board Told-November 8, 1989

Zoning consultant Philip B. Herr warned the Norwood Planning Board that unchecked Route 1 development and traffic could trigger a state-imposed growth freeze led by Secretary of Environmental Affairs John DeVillars.
-
Planning Board Member Rudith Berkowitz Calls for Building Moratorium Amid Out-of-Control Growth Concerns-October 20, 1987

Berkowitz Urges Moratorium at Public Hearing on Nahatan Street Apartments Voicing sharp frustration over rapid development, Norwood Planning Board member Rudith Berkowitz called for a townwide building moratorium last night as an essential first step toward halting what she termed “out-of-control growth.” Berkowitz’s impassioned remarks came during a heated public hearing regarding a proposal by…
-
Norwood Airport Manager Submits Residential Housing Proposal to Planning Board-August 13, 1985

Boston Municipal Airport proposed 21 single-family homes at the end of Hazelwood Drive, while the planning board reviewed Route 1 park modifications.
-
Planning Board Proposes Water Resources Protection District to Safeguard Ellis Well Field-August 14, 1984

Norwood’s planning board voted to place a water resources protection district zoning bylaw on the September 24 special town meeting warrant to protect the Ellis Avenue well field.
-
Groundbreaking Held for $28 Million Norwood Hospital Addition After Decade of Planning-September 28, 1981

Governor Edward J. King and local leaders break ground on Norwood Hospital’s $28 million, five-story addition, marking the end of a decade of planning and regulatory hurdles.
-
Winslow Office Plan Gets Official Backing-June 9, 1981

Norwood officials clear the path to transform the closed Winslow School into professional office condominiums, winning broad neighborhood support.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.