Norwood High School’s $5 million renovation project will not be completed by the time classes are scheduled to resume on September 3, the project contractor informed town officials. Thomas Boyle, owner of Anchor Construction Co. of Lowell, stated during a joint meeting that the facility will not be ready for occupancy until October 15 at the earliest, citing persistent subcontractor issues and late material deliveries.
Major construction work remains incomplete on corridor floors and ceilings, heating and electrical systems, and critical safety infrastructure, including fire alarms and sprinkler systems, though most classroom work is finished. School Superintendent James Savage told the building committee that officials face costly decisions regarding temporary student housing, noting that the strongest alternative is utilizing the vacant Junior High School North. When building committee member Edward McDonough asked Boyle if he would bank on a September 3 opening, Boyle candidly replied, “No, in my opinion, if you can put those kids someplace else, put them someplace else.”
While construction supervisor Daniel Egan noted that 108 workers remain on site, missing key shipments—such as fire doors and heating ventilators—prevent building inspectors from granting occupancy. Committee members and project architect Richard Heydecker, along with high school Principal John Piccirilli and school committee Chairman Richard Kief, reviewed options including early dismissals or partial occupancy. However, Superintendent Savage cautioned that construction noise and uncompleted cafeterias would severely disrupt instruction, while Heydecker warned that environmental controls on the new heating system might remain unstable through January. The school committee scheduled a follow-up meeting to determine final student placement.
(Reporting by Bernie McEvoy, The Patriot Ledger).
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Norwood Zeroes In On School Vandals-August 3, 1977

A newly formed blue‑ribbon security committee convened to confront a surge of costly vandalism at Norwood’s public schools. Members reviewed structural, technological, and community‑based deterrents while assigning formal research duties for a comprehensive townwide response.
-
Public Schools Enrollment Down 341 Students, Though Upcoming Apartment Construction Expected to Boost Numbers-September 16, 1976

Norwood school officials report a drop of 341 students in total enrollment, but anticipate new apartment construction will push numbers back up.
-
Louis Buscone Jr. Appointed High School Vice-Principal After Close School Committee Vote-September 9, 1976

Louis Buscone Jr. wins a one-year appointment as Norwood High School vice-principal by a 4-3 school committee vote as the board reviews declining enrollment figures.
-
Norwood School Committee Seeks Field Trip Funds and Awards Bus Transportation Contracts-July 29, 1976

Facing budget cuts that eliminated student field trips, the Norwood School Committee voted to appeal to the Finance Commission and special town meeting for restoration funds.
-
Norwood Board Rejects Blue Hills Collaborative-July 29, 1976

The summer of 1976 was a time of great change and uncertainty for the town of Norwood, Massachusetts. As the nation celebrated its bicentennial, local residents were grappling with issues of education, finance, and community involvement. One such issue that dominated the headlines in July 1976 was the proposed Blue Hills Collaborative, a vocational school…
-
Balch School Welcomes First Full-Time Bilingual Teacher for Growing Portuguese Student Community-October 24, 1975

Driven by parent advocacy led by Manuel DaCosta, the Balch School welcomed its first full-time bilingual teacher, Mrs. Diane Lawrence Callahan, to support Norwood’s growing Portuguese student population.
-
Balch School Library to Be Officially Dedicated as Grace M. Beverly Memorial Library-October 23, 1975

The Balch School library in South Norwood will be dedicated as the Grace M. Beverly Memorial Library, honoring the beloved former principal’s lifelong dedication to children’s literature and education.
-
Oldham School Sixth Graders Discover an Outdoor Classroom During Rainy New Hampshire Wilderness Trip-October 9, 1975

Oldham School sixth graders brave a rainy week of hiking, craft-making, and ecology studies during an outdoor education field trip to New Hampshire.
-
School Committee Reviews Standardized Test Results-September 18, 1975

Norwood School Committee reviews standardized test results, prompting officials to push for a return to basics in math and language skills across all grade levels.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.