Norwood High School’s $5 million renovation project will not be completed by the time classes are scheduled to resume on September 3, the project contractor informed town officials. Thomas Boyle, owner of Anchor Construction Co. of Lowell, stated during a joint meeting that the facility will not be ready for occupancy until October 15 at the earliest, citing persistent subcontractor issues and late material deliveries.
Major construction work remains incomplete on corridor floors and ceilings, heating and electrical systems, and critical safety infrastructure, including fire alarms and sprinkler systems, though most classroom work is finished. School Superintendent James Savage told the building committee that officials face costly decisions regarding temporary student housing, noting that the strongest alternative is utilizing the vacant Junior High School North. When building committee member Edward McDonough asked Boyle if he would bank on a September 3 opening, Boyle candidly replied, “No, in my opinion, if you can put those kids someplace else, put them someplace else.”
While construction supervisor Daniel Egan noted that 108 workers remain on site, missing key shipments—such as fire doors and heating ventilators—prevent building inspectors from granting occupancy. Committee members and project architect Richard Heydecker, along with high school Principal John Piccirilli and school committee Chairman Richard Kief, reviewed options including early dismissals or partial occupancy. However, Superintendent Savage cautioned that construction noise and uncompleted cafeterias would severely disrupt instruction, while Heydecker warned that environmental controls on the new heating system might remain unstable through January. The school committee scheduled a follow-up meeting to determine final student placement.
(Reporting by Bernie McEvoy, The Patriot Ledger).
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Norwood School Committee Narrows Superintendent Search to Three Finalists, Including Junior High North Principal James R. Savage-August 11, 1982

Junior High North Principal James R. Savage was named one of three finalists for Norwood superintendent of schools, alongside Arlington assistant superintendent William J. Birmingham and Rhode Island administrator Nora M. Walker.
-
Peabody School Graduates Told Of Obligation To Support Education-June 25, 1982

School officials emphasize community obligations and moral commitments to public education during exercises at Junior High School South.
-
Norwood High School 1962 Addition Cleared of Asbestos Hazards in State Safety Survey-November 3, 1981

Following state inspections of regional schools built between 1946 and 1972, Norwood High School has been cleared of asbestos hazards, with reinspection set for next year.
-
Junior High South Approves ‘Project Adventure’ Obstacle Course Gym Class-October 15, 1981

Junior High South introduces “Project Adventure,” an outdoor physical education obstacle course designed to build teamwork and move away from competitive sports.
-
Norwood High School Senior Edward J. Skricki Named Merit Scholarship Semi-Finalist; Three Peers Commended-October 13, 1981

Norwood High senior Edward J. Skricki achieves National Merit Scholarship semi-finalist standing, joined by commended classmates Judith Martowska, Susan O’Brien, and Joseph Petrie Jr.
-
Superintendent Taris Seeks to Curb Rising Costs of After-Hours School Building Use-September 4, 1981

Superintendent of Schools Louis J. Taris is pushing to rein in the surging volume of outside organizations utilizing school facilities during evening and weekend hours, citing mounting financial burdens on the school department. Dr. Taris informed the school committee that dozens of local organizations currently utilize school buildings after hours, frequently without paying any rental…
-
Norwood School Committee Votes Eliminate Youth Hangout-July 31, 1981

Following rampant vandalism, late-night drinking, and brush fires near Callahan Elementary School, the Norwood School Committee voted to fund a $6,000 clearing project to eliminate a notorious youth hangout.
-
School Committee Awards New Transportation Contracts-July 16, 1981

After a difficult budget cycle in 1980, the committee avoided controversy by budgeting accurately and selecting trusted local transportation providers.
-
It’s Time to Decide on Fate of Old High School-November 10, 1980

Facing Proposition 2½ and declining enrollments, Norwood school leaders are evaluating a 39-page NEASC report calling for urgent renovations to the high school, particularly its library media center.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.