Norwood High School’s $5 million renovation project will not be completed by the time classes are scheduled to resume on September 3, the project contractor informed town officials. Thomas Boyle, owner of Anchor Construction Co. of Lowell, stated during a joint meeting that the facility will not be ready for occupancy until October 15 at the earliest, citing persistent subcontractor issues and late material deliveries.

Major construction work remains incomplete on corridor floors and ceilings, heating and electrical systems, and critical safety infrastructure, including fire alarms and sprinkler systems, though most classroom work is finished. School Superintendent James Savage told the building committee that officials face costly decisions regarding temporary student housing, noting that the strongest alternative is utilizing the vacant Junior High School North. When building committee member Edward McDonough asked Boyle if he would bank on a September 3 opening, Boyle candidly replied, “No, in my opinion, if you can put those kids someplace else, put them someplace else.”

While construction supervisor Daniel Egan noted that 108 workers remain on site, missing key shipments—such as fire doors and heating ventilators—prevent building inspectors from granting occupancy. Committee members and project architect Richard Heydecker, along with high school Principal John Piccirilli and school committee Chairman Richard Kief, reviewed options including early dismissals or partial occupancy. However, Superintendent Savage cautioned that construction noise and uncompleted cafeterias would severely disrupt instruction, while Heydecker warned that environmental controls on the new heating system might remain unstable through January. The school committee scheduled a follow-up meeting to determine final student placement.

(Reporting by Bernie McEvoy, The Patriot Ledger).

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood School Committee Approves Balch School Remedial Class and Eight-Period High School Day-July 31, 1975

    The Norwood School Committee approved a pilot transitional first grade and modified kindergarten at Balch School to address kindergarten screening results and language needs.

  • School Committee Approves Shortened High School Day Format-July 16, 1975

    The school committee of Norwood last night all but formally approved a switch to a shorter, eight-period day for the high school. The decision was made in response to a request from absent member Richard Joseph, who asked that the board defer its official vote on the plan until its next regular meeting in two…

    Square vintage clock on tiled school hallway wall showing 2:30
  • Willett School Overcrowding And Parent Protests-September 5, 1974

    Angry parents confront the Norwood School Committee over severe overcrowding at the Willett School, while officials address elementary enrollment spikes and pedestrian safety.

  • Youth Enriched at Summer School-August 13, 1974

    Directing over 600 local students, Norwood’s public summer school program completed its 30-day session, highlighting strong popularity for enrichment classes in arts and trades alongside vital remedial and special education tutoring.

  • Norwood School Committee Votes to Relocate School Administration Offices-August 1, 1974

    The Norwood School Committee voted 5-2 to relocate central school administration offices to the Winslow School, pending cost estimates from Superintendent Philip O. Coakley.

  • Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

    After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.

  • Unfinished Junior High To Open On Schedule-July 8, 1974

    Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.

  • School Board Rejects ‘Floating Principal’ Proposal-July 03, 1974

    The Norwood School Committee held a contentious session on the evening of July 2, 1974, where, following two weeks of deliberation and a lengthy 90-minute executive session, the board voted 5-1 to reject a proposal to create a new administrative position titled “floating principal.“ The concept, initially championed by Committee Member Joseph M. Pentowski, was…

    Silhouettes of students running through shattered walls with arrows labeled growth, population, overcrowding, and expansion in a school-themed comic style
  • School Drop-In Centers Possible In Fall-June 24, 1974

    Citing summer custodial constraints and a lack of air conditioning, town officials vote to survey local youths during the summer to prepare for a fall launch.

    School hallway with blue lockers, wooden floor, sunlight streaming through large windows, and signs for art wing
  • Public Schools Face Delays and Possible State Action on Mandatory Hot Lunch Program-August 31, 1973

    Parents of elementary school students in Norwood will need to continue packing brown-bag lunches for the start of the academic year. School Superintendent Philip O. Coakley announced that the town will fail to meet the state-mandated September deadline for implementing a universal public school hot lunch program, exposing the municipality to potential legal action by…


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.