Norwood High School’s $5 million renovation project will not be completed by the time classes are scheduled to resume on September 3, the project contractor informed town officials. Thomas Boyle, owner of Anchor Construction Co. of Lowell, stated during a joint meeting that the facility will not be ready for occupancy until October 15 at the earliest, citing persistent subcontractor issues and late material deliveries.

Major construction work remains incomplete on corridor floors and ceilings, heating and electrical systems, and critical safety infrastructure, including fire alarms and sprinkler systems, though most classroom work is finished. School Superintendent James Savage told the building committee that officials face costly decisions regarding temporary student housing, noting that the strongest alternative is utilizing the vacant Junior High School North. When building committee member Edward McDonough asked Boyle if he would bank on a September 3 opening, Boyle candidly replied, “No, in my opinion, if you can put those kids someplace else, put them someplace else.”

While construction supervisor Daniel Egan noted that 108 workers remain on site, missing key shipments—such as fire doors and heating ventilators—prevent building inspectors from granting occupancy. Committee members and project architect Richard Heydecker, along with high school Principal John Piccirilli and school committee Chairman Richard Kief, reviewed options including early dismissals or partial occupancy. However, Superintendent Savage cautioned that construction noise and uncompleted cafeterias would severely disrupt instruction, while Heydecker warned that environmental controls on the new heating system might remain unstable through January. The school committee scheduled a follow-up meeting to determine final student placement.

(Reporting by Bernie McEvoy, The Patriot Ledger).

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood School Administration Relocates to Willett School-July 24, 1980

    The Norwood School Administration relocated to the George F. Willett School and enacted strict new graduation credit requirements.

  • Students to Face Stiffer Standards-July 18, 1990

    In 1990 the town of Norwood was on the cusp of a significant change in its educational system. The school administration, led by Superintendent Louis J. Taris, had been studying ways to improve academic standards for over a year and a half. The result of this study was a proposal to double the number of…

  • School Enrollment Shows Drop of 382 from Last Year-September 6, 1979

    Norwood public school enrollment drops by 382 students to 5,078, while administrators outline major scheduling and open-campus policy changes at the senior high school.

  • Aaron Guild School Leased to Norwood CETA Consortium and EdCo for One Year-August 1, 1979

    Norwood selectmen voted unanimously to lease the closed Aaron Guild School for one year to the Norwood CETA Consortium and the Educational Collaborative of Greater Boston (EdCo) for $148,000.

  • Norwood School Bus Billing Questioned-July 31, 1979

    The Patriot Ledger’s July 31, 1979 edition brought to light a controversy surrounding the billing practices of Kiessling School Transportation of Dedham, which had been contracted by the town of Norwood to transport special needs children. The issue at hand was whether the company had overcharged the town for mileage on certain routes. According to…

  • School Department Releases Bus Routes and Eligibility Rules-August 30, 1978

    As the late-summer excitement of a new academic year approached in 1978, the Norwood School Department officially released its comprehensive student transportation schedules, route mappings, and eligibility guidelines for the upcoming school term. Designed to ensure safe and orderly transit for thousands of local students, the announcement established clear boundaries and behavioral expectations for families…

  • Norwood School Committee Considers Staggered School Closing Plan-July 14, 1978

    The school housing needs committee last night recommended a second school closing plan that would close the doors of the Callahan School in September, shut down the Balch School in 1981 and close a third, unnamed elementary school in 1983. The plan was backed by seven of the nine members voting and was billed as…

  • Norwood High School Accessibility Concerns-July 10, 1978

    On July 10, 1978, parents of handicapped students in Norwood voiced serious concerns regarding the lack of physical accessibility at the local high school. Mrs. Charlotte Haskell, president of the Norwood Special Needs Parents Group, recently sent a formal letter to School Superintendent Philip O. Coakley. In the communication, she urged the district to take…

  • School Board Recall Urged-July 8, 1978

    Discover the 1978 budget battle in Norwood, where deep cuts to the school district’s $11.3 million budget led to a controversial recall effort and a lawsuit involving the Massachusetts Teachers Association.

  • Taxpayers Sue to Restore School Budget-July 6, 1978

    Seeking to prevent a mid-summer school closure, 36 Norwood taxpayers filed a lawsuit in 1978 to restore $600,000 in education funding.

    Stacked textbooks for school subjects topped with bundles of cash in a classroom

Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.