Selectmen Seek $210,000 at Special Town Meeting to Replace Temporary Military Bailey Span Installed After March 1968 Flood
DEDHAM – Norfolk County Commissioners formally approved Norwood’s municipal blueprint for reconstructing the Pleasant Street bridge on Tuesday, November 18, 1969, clearing a critical jurisdictional hurdle on the eve of a Special Town Meeting vote to fund the long-awaited span. Reported in The Patriot Ledger on Wednesday, November 19, 1969, the county board dispatched a letter to Norwood granting official permission for the reconstruction—necessary because Pleasant Street was designated a county way requiring commission consent prior to any structural rebuilding.
Earlier in the month, county commissioners had agreed to act on Norwood’s proposal before Town Meeting convened so voters would know the project had county backing. During negotiations, Norwood officials firmly rejected an alternative county engineering concept that would have relocated the roadway alignment alongside rebuilding the bridge, arguing that the added right-of-way and road-relocation costs were financially prohibitive for the town.
The permanent replacement was urgently needed after the original Pleasant Street span was washed out during the severe March 1968 regional flooding. Since that disaster, traffic along Pleasant Street had relied on a temporary steel “Bailey” bridge on loan from the Commonwealth of Massachusetts—an emergency military-style truss span subject to recall by state highway authorities at any time.
To begin construction immediately, the Norwood Board of Selectmen placed an article on the warrant for Thursday night’s Special Town Meeting requesting a $210,000 appropriation to build the new bridge. Under the financing breakdown outlined by selectmen, $90,000 of that total was expected to be reimbursed through state and federal emergency flood-relief funds, supplemented by a potential $15,000 matching grant from the state Department of Waterways. While the Norwood Finance Commission recommended passage of the Special Town Meeting article, FinCom noted that officials had not yet confirmed whether state Chapter 90 highway funds would also be available to offset the local share of the project, which needed to get underway without delay.
1969 Pleasant Street Bridge Funding Adjusted to 2026 Dollars & Site Legacy
Inflation-adjusted using U.S. Bureau of Labor Statistics CPI data ($1.00 in Nov. 1969 ≈ $8.73 in 2026)
| 1969 Bridge Reconstruction Funding Item | 1969 Amount | 2026 Equivalent |
|---|---|---|
| Total Special Town Meeting Bridge Appropriation | $210,000 | ~$1,833,300 |
| Expected State & Federal Emergency Flood Relief Reimbursement | $90,000 | ~$785,700 |
| Potential State Department of Waterways Matching Grant | $15,000 | ~$130,950 |
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Selectmen Approve Upland Road and Clapboardtree Street Infrastructure Project-July 13, 1971

Local leaders also enacted emergency measures for the town dump to comply with state sanitary regulations and adjusted the 1971 tax rate through light department fund transfers.
-
Engineers Estimate $532,000 Cost for University Avenue Extension-September 4, 1970

A four-month overdue engineering study prepared by Boston-based consultants Fay, Spofford & Thorndike Inc. at a cost of $8,000 has placed an estimated price tag of $532,000 on the proposed 2,700-foot extension of University Avenue. The recommended roadway layout will connect the existing portion of University Avenue with Everett Street just before intersecting Route 1,…
-
Route 1 Median Guard Rail and Safety Construction Nearing December Completion-October 15, 1969

Crews install median guard rails and chain-link safety fencing along Route 1 across Norwood, Westwood, and Dedham, with a target completion date of December.
-
Norwood Kills Funds For School Addition-June 26, 1969

Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.
-
State Unveils Route 1 and Everett Street Intersection Plans Ahead of Polaroid Complex Opening-November 19, 1968

State DPW engineer Michael J. Mahoney told Norwood officials in November 1968 that widening Everett Street and adding Route 1 turning lanes would handle traffic from Polaroid’s 1,200-worker Forbes Estate plant until 1990 without a highway interchange.
-
Norwood Voters To Consider Lighting Funds-June 26, 1968

The Finance Commission backs the utility expansion alongside a $163,000 sewer construction article, while the town master plan is deferred.
-
Industrial Commission Welcomes Star Service Hub-June 30, 1967

Following 50 intensive town meetings to resolve department regulations, developers project the new multi-million square foot industrial hub will lower Norwood’s local tax rate.
-
Ask Town Meeting on Industrial Park-September 7, 1966

Representatives of the development firm Cabot, Cabot & Forbes (CC&F) urged the Board of Selectmen last night to place an article before an early October special town meeting to pave the way for major infrastructure development at the Norwood Industrial Park. C. Brooks Dodge, representing CC&F, asked the board to initiate town meeting action and…
-
State Traffic Engineers Investigate Missing Stop Sign Reports in Norwood-August 31, 1966

Local frustration over municipal traffic safety measures came to a head when town officials addressed long-standing delays regarding state approval for stop signs at key intersections. Commenting on the sluggish bureaucratic pace, one local selectman dryly remarked, “It takes an act of God to post a stop sign!” The exasperation stemmed from a nine-month delay…