Selectmen Seek $210,000 at Special Town Meeting to Replace Temporary Military Bailey Span Installed After March 1968 Flood

DEDHAM – Norfolk County Commissioners formally approved Norwood’s municipal blueprint for reconstructing the Pleasant Street bridge on Tuesday, November 18, 1969, clearing a critical jurisdictional hurdle on the eve of a Special Town Meeting vote to fund the long-awaited span. Reported in The Patriot Ledger on Wednesday, November 19, 1969, the county board dispatched a letter to Norwood granting official permission for the reconstruction—necessary because Pleasant Street was designated a county way requiring commission consent prior to any structural rebuilding.

Earlier in the month, county commissioners had agreed to act on Norwood’s proposal before Town Meeting convened so voters would know the project had county backing. During negotiations, Norwood officials firmly rejected an alternative county engineering concept that would have relocated the roadway alignment alongside rebuilding the bridge, arguing that the added right-of-way and road-relocation costs were financially prohibitive for the town.

The permanent replacement was urgently needed after the original Pleasant Street span was washed out during the severe March 1968 regional flooding. Since that disaster, traffic along Pleasant Street had relied on a temporary steel “Bailey” bridge on loan from the Commonwealth of Massachusetts—an emergency military-style truss span subject to recall by state highway authorities at any time.

To begin construction immediately, the Norwood Board of Selectmen placed an article on the warrant for Thursday night’s Special Town Meeting requesting a $210,000 appropriation to build the new bridge. Under the financing breakdown outlined by selectmen, $90,000 of that total was expected to be reimbursed through state and federal emergency flood-relief funds, supplemented by a potential $15,000 matching grant from the state Department of Waterways. While the Norwood Finance Commission recommended passage of the Special Town Meeting article, FinCom noted that officials had not yet confirmed whether state Chapter 90 highway funds would also be available to offset the local share of the project, which needed to get underway without delay.

1969 Pleasant Street Bridge Funding Adjusted to 2026 Dollars & Site Legacy

Inflation-adjusted using U.S. Bureau of Labor Statistics CPI data ($1.00 in Nov. 1969 ≈ $8.73 in 2026)

1969 Bridge Reconstruction Funding Item 1969 Amount 2026 Equivalent
Total Special Town Meeting Bridge Appropriation $210,000 ~$1,833,300
Expected State & Federal Emergency Flood Relief Reimbursement $90,000 ~$785,700
Potential State Department of Waterways Matching Grant $15,000 ~$130,950
Site Today (2026): Located along Pleasant Street crossing the Neponset River corridor in South Norwood, the permanent bridge replaced the post-1968 flood Bailey span and continues to serve as a key north-south arterial roadway connecting South Norwood with Route 1 and neighboring Walpole.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.