Representatives of the development firm Cabot, Cabot & Forbes (CC&F) urged the Board of Selectmen last night to place an article before an early October special town meeting to pave the way for major infrastructure development at the Norwood Industrial Park.
C. Brooks Dodge, representing CC&F, asked the board to initiate town meeting action and secure $15,000 for the town’s share of constructing a rail underpass at Canton Street—a crucial prerequisite for extending rail service from the Westwood Industrial Park across Canton Street into the Norwood park. The underpass project is estimated at $125,000 total, split under a county formula where the state covers roughly 50 percent, the county 25 percent, and Norwood, Westwood, and Canton share the remainder. However, Canton selectmen recently notified the county that their support for the park plans does not extend to financing.
The development hinges heavily on a proposed 30-acre warehousing complex by Star Market on a 55-acre site. Dodge noted that CC&F will not contribute to road construction costs, and warned officials that cooperation from local abutters may be difficult to secure. To accommodate the Star Market facility, selectmen will also be asked to consider seven zoning bylaw changes, which would permit on-site incineration, a food preparation kitchen, an employee cafeteria, a vehicle repair garage, and modified parking requirements.
“Road A” Costs and Land Valuation
The primary cost article involves “Road A,” an extension running 7,200 feet from Canton Street to American Way, carrying an estimated price tag of $620,000. While selectmen previously hesitated to build infrastructure on speculation, Selectman Walter Dempsey argued that construction costs will only rise, noting, “It is never going to be any cheaper than it is now.”
The planning board report highlights that prepared land in the Westwood park sold for about $35,000 per acre three years ago and now commands upwards of $50,000 per acre, while valuation for the 417 acres in the Norwood park totals $29,950. Selectmen authorized Town Manager Walter Blasenak, Town Engineer Robert Hamilton, and municipal consultants to meet with CC&F engineers to review road layouts, utility costs, and land assessments.
Additional Municipal Actions
In other business, the board:
- Agreed to insert an article in the warrant for $995 to purchase a radar traffic control unit following a recommendation by Police Chief James M. Murphy, who also requested new speed limit and warning signs near Neponset Street, Route 1A, and I-95 approaches.
- Voted to ask the town personnel board to consider a 6 percent cost-of-living increase for all municipal employees, following a request by Highway Superintendent William E. McCarthy.
- Proposed installing traffic control lighting at the Neponset and I-95 street circles and the Wilson Street intersection to mitigate traffic hazards.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
State Approves Traffic Barrier to Block East Cross Street Access from Route 1-August 12, 1988
Following a resident petition led by Joseph Burke and Rep. Gregory Sullivan after a child’s injury, the state approved a barrier blocking Route 1 access to East Cross Street.

-
Norwood Committee Faults T Study-July 9, 1987
Discover the 1987 conflict between the Norwood Parking Committee and the MBTA regarding station parking statistics and the pushback against multi-level parking deck plans at the Norwood Depot.

-
SOfficials Tour Ellis Pond Dam and Meadow Brook Sites-August 22, 1984
State Waterways Director John J. Hannon joined Norwood officials to inspect Ellis Pond Dam and the Meadow Brook watershed, targeting $850,000 in state funds toward critical flood mitigation.

-
Adams-Russell Cable Services Tells Norwood Selectmen Local Cable System is Completed-August 8, 1984
Company Announces Energizing of Public Institutional Loop as Two-Year Rate Freeze Certification Process Approaches NORWOOD — Representatives from Adams-Russell Cable Services informed town selectmen last night that Norwood’s cable television system is officially complete. The declaration marks a critical milestone for both the Waltham-based company and local subscribers, as certification triggers the start of a…

-
Guild School Recreation Center Project & Eliot Field Renovation-August 26, 1980
The Norwood Permanent Building Committee selected six architectural firms to interview for the Guild School renovation project, while Norwood Engineering secured the Eliot Field design contract.

-
Guild School Picked for Civic Center-July 8, 1980
Discover the 1980 decision that transformed the Aaron Guild School into a multi-purpose recreation hub, replacing the former Civic Center sold to Norwood Hospital.

-
Norwood Selectmen Consider One-Way Traffic, Business District Upgrades-August 8, 1979
Building on the Washington Street revitalization project, Town Manager John J. Carroll proposed working with local merchants to secure a second Urban Systems grant for Nahatan Street improvements.