The Norwood Permanent Building Committee announced that six architectural firms have been invited to submit proposals and participate in September interviews for the major renovation of the Guild School into a new community recreation center. Committee Chairman Roger Pellitier noted that the firms responded directly to advertisements placed in professional publications, though additional firms may still be considered.
The six competing architectural firms asked to submit proposals are:
- Drummey Rosane Anderson of Newton
- Korslund, LeNormand & Quann Inc. of Norwood
- Brian G. Novack Associates of Norwood
- Campbell & Searson of Cambridge
- TAMS of Boston
- Rich, Lang & Cote Inc. of Newton
Eliot Field Renovation and Recreation Scheduling
In related municipal recreation updates, the contract to design and oversee the renovation of Eliot Field in South Norwood—which is slated to replace the existing Civic Center field—has been awarded to Norwood Engineering.
With Norwood Hospital scheduled to take over the current Civic Center field property next summer, local residents and sports leagues raised concerns regarding potential field shortages for the upcoming baseball season. However, Pellitier assured the community that the recreation department has successfully arranged to reschedule affected games to alternative fields. Furthermore, Pellitier explained that the extended timeline will benefit the project: “Eliot Field will have an extra growing season after renovations are complete,” with the new facility expected to open in the spring of 1982.
To fund the physical construction of both the Guild School recreation center and the Eliot Field upgrades, officials anticipate that a special town meeting will be called later in the fall to appropriate the necessary capital funds.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Selectmen Approve Infrastructure Improvements for Upland Road-July 12, 1971
Local leaders also enacted emergency measures for the town dump to comply with state sanitary regulations and adjusted the 1971 tax rate through light department fund transfers.

-
Selectmen Approve Upland Road and Clapboardtree Street Infrastructure Project-July 13, 1971
Local leaders also enacted emergency measures for the town dump to comply with state sanitary regulations and adjusted the 1971 tax rate through light department fund transfers.

-
Engineers Estimate $532,000 Cost for University Avenue Extension-September 4, 1970
A four-month overdue engineering study prepared by Boston-based consultants Fay, Spofford & Thorndike Inc. at a cost of $8,000 has placed an estimated price tag of $532,000 on the proposed 2,700-foot extension of University Avenue. The recommended roadway layout will connect the existing portion of University Avenue with Everett Street just before intersecting Route 1,…

-
Norwood Kills Funds For School Addition-June 26, 1969
Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

-
Norwood Voters To Consider Lighting Funds-June 26, 1968
The Finance Commission backs the utility expansion alongside a $163,000 sewer construction article, while the town master plan is deferred.

-
Industrial Commission Welcomes Star Service Hub-June 30, 1967
Following 50 intensive town meetings to resolve department regulations, developers project the new multi-million square foot industrial hub will lower Norwood’s local tax rate.

-
Ask Town Meeting on Industrial Park-September 7, 1966
Representatives of the development firm Cabot, Cabot & Forbes (CC&F) urged the Board of Selectmen last night to place an article before an early October special town meeting to pave the way for major infrastructure development at the Norwood Industrial Park. C. Brooks Dodge, representing CC&F, asked the board to initiate town meeting action and…

-
State Traffic Engineers Investigate Missing Stop Sign Reports in Norwood-August 31, 1966
Local frustration over municipal traffic safety measures came to a head when town officials addressed long-standing delays regarding state approval for stop signs at key intersections. Commenting on the sluggish bureaucratic pace, one local selectman dryly remarked, “It takes an act of God to post a stop sign!” The exasperation stemmed from a nine-month delay…

-
Oldham School Drainage Repairs Scheduled For Completion-June 24, 1964
Corrective Measures Target Long-Standing Controversy At Elementary Site Corrective measures designed to resolve persisting drainage problems at the Oldham Elementary School are scheduled to be completed by the end of this week. The ongoing drainage difficulties at the new school site had been the subject of a long controversy in discussions of the Oldham School…