40 Percent State Reimbursement Cleared for $4 Million Junior High and Elementary Projects as Committee Debates Gas vs. Electric Heating
NORWOOD – The Massachusetts School Building Assistance Commission granted preliminary plan approval on Thursday, November 17, 1966, for the construction of two major new public schools in Norwood—clearing the way for a 40 percent state construction reimbursement on the proposed $4 million combined junior high and elementary school program. Announced by Permanent Building Committee Chairman Justin C. Barton on Thursday night and reported in The Patriot Ledger on Friday, November 18, 1966, the approval came just weeks ahead of a Special Town Meeting scheduled by selectmen for December 8.
The December 8 warrant was set to feature seven articles sponsored by the Permanent Building Committee, led by proposals to construct and equip a 16-room elementary school near Westover Parkway—including transferring the town-owned Westover site to school-use designation and abandoning a portion of the parkway—alongside constructing and equipping a 30-room junior high school adjacent to the Father MacAleer Playground, accompanied by an article to acquire roughly eight acres of land by eminent domain. In a key consensus step, the School Housing Needs Committee voted to endorse both sites selected by Barton’s panel, reversing its prior preference for a Wilson Street elementary school site after Town Meeting had rejected both Wilson Street and Father MacAleer the previous year. Barton explained that after evaluating eight candidate locations, his committee favored Westover over Wilson Street because the Wilson Street parcel posed an $82,000 drainage problem and would still remain inadequate in size.
Pressed for both time and pre-construction funding, however, the Permanent Building Committee voted Thursday night to postpone action on extending utilities and transferring the Westover parcel until a later date because it lacked funds to prepare formal engineering plans. Instead, the panel prepared a December 8 warrant article requesting $5,000 for legal, engineering, and clerical expenses.
Other capital items slated for the December 8 warrant included a $390,400 appropriation for an addition and renovation at the Norwood Civic Center / Recreation Center, bolstered by more than $110,000 from the Veterans Memorial fund. Selectman Walter J. Dempsey noted that while Town Meeting had voted to accept the Veterans Memorial contribution, the Massachusetts Attorney General’s office would not approve the fund transfer until the town appropriated its municipal share. Town Counsel Walter J. Gotovich was asked to draft the exact appropriation wording and determine whether separate articles were required for the recreation center addition and renovation, while a separate warrant article also recommended constructing a new municipal cemetery garage with multiple construction cost estimates to be presented at the meeting.
Meanwhile, a sharp technical debate flared over how to heat the new schools. Building committee member John Mogan presented a proposal from the Norwood Gas Co. claiming substantial installation and operating savings over the committee’s previously endorsed all-electric heating system, prompting Mogan to ask for reconsideration of the prior week’s vote. Based on actual operating figures from Easthampton High School, Norwood Gas Co. projected an initial installation cost of $381,200 for gas heating and lighting at the junior high school—compared to $443,833 for electric heat due to heavier wiring, extra insulation, and double glazing—alongside annual operating costs of $20,897 for gas versus $24,262 for electric. Heating consultant Charles Crowley had dismissed gas boiler systems the previous week as three times as expensive as oil or electric, and architect Robert J. Searson Jr. of Korslund, LeNormand and Quann voiced hesitation over Norwood Gas Co.’s hybrid design combining boilers with individualized classroom heaters encased in cinder-block compartments, warning it would create an inflexible classroom layout. Committee members asked Crowley to conduct a direct cost comparison between Mogan’s gas figures and the electric estimates ahead of Town Meeting.
1966 School Building Costs Adjusted to 2026 Dollars & Site Legacy
Inflation-adjusted using U.S. Bureau of Labor Statistics CPI data ($1.00 in Nov. 1966 ≈ $9.84 in 2026)
| 1966 Municipal Project / Estimate | 1966 Amount | 2026 Equivalent |
|---|---|---|
| Combined Junior High & Elementary School Program | $4,000,000 | ~$39,360,000 |
| Electric Heating System Initial Cost (Junior High) | $443,833 | ~$4,367,317 |
| Recreation Center Addition & Renovation Request | $390,400 | ~$3,841,536 |
| Gas Heating System Initial Cost (Junior High) | $381,200 | ~$3,751,008 |
| Veterans Memorial Fund Contribution | $110,000+ | ~$1,082,400+ |
| Wilson Street Site Drainage Cost Estimate | $82,000 | ~$806,880 |
| Legal, Engineering & Clerical Article | $5,000 | ~$49,200 |
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…
-
Norwood Adopts Whitman-Hanson School Prototype Model to Save Time and Money on New High School Construction-September 13, 2008

Norwood attempts to save time and money on its new high school construction project by reusing the architectural blueprints of Whitman-Hanson Regional High School.
-
Norwood High School Renovation Plans Scrapped in Favor of New Building-October 15, 2005

Facing accreditation warnings and failing infrastructure, Norwood’s School Facility Task Force votes overwhelmingly to pursue a new high school building.
-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.
-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985

Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.
-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976

Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.
-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974

Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.