Contractors installing a new sprinkler system at Norwood High School assured the Permanent Building Committee last night that construction will be finished by next Friday, keeping the scheduled September 8 opening date on track.
Project Manager Robert Devoe of Boston’s ABC Sprinkler Co. stated that work will be 98 percent complete by Friday and announced he will personally oversee a second shift of workers starting Monday. The reassurance came after Assistant Superintendent James R. Donovan voiced concerns to the school committee on Wednesday night that installation delays might postpone the start of the academic year. Devoe noted that the cafeteria remains the only major area pending completion, after which the system will undergo rigorous pressure testing.
Engineering Friction and Gym Renovations
Committee members and contractors expressed frustration with Francis J. Thompson of HPR Services of New Hampshire, the engineer responsible for calculating the placement of over 800 sprinkler heads. Vice-Chairman Philip C. Swain reported that a minor calculation error by Thompson stalled necessary project approval from the Insurance Service Office (ISO). Committee members noted they had spent three weeks unsuccessfully trying to get Thompson to meet with the ISO, prompting a phone call and message left at his home during the meeting.
In other facility updates, Vincent Carlson—project manager for Korslund, LeNormand & Quann Inc. supervising high school renovations—reported that gym floor sanding is over 50 percent complete and expected to finish by Wednesday, allowing the application of the first of four finish coats and subsequent court line painting. While the gym floor will not be fully ready by the exact opening day of school, the building’s fire alarm system is scheduled for testing today. Carlson added that a temporary indicator panel has been installed at the insistence of the fire department until the permanent factory unit arrives, which will eventually tie in the completed sprinkler system.
Student Registration and Daily School Schedules
The school department announced registration and schedule guidelines for the upcoming 1976–77 academic year:
- New Student Registration: Open for students entering the Norwood school system for the first time at all school administrative offices, Monday through Friday from 9:00 a.m. to noon and 1:00 to 3:00 p.m. Parents must provide birth and immunization certificates.
- School Opening & Screening: All public schools open on September 8. Kindergarten screening runs from September 8 to 14, with kindergarten classes commencing September 15.
- Daily Time Schedules:
- High School & Henry O. Peabody School: 7:45 a.m. to approximately 2:30 p.m.
- North & South Junior High Schools: 7:45 a.m. to 2:20 p.m.
- Elementary Schools: 8:40 a.m. to 2:55 p.m.
- Kindergarten: Morning session from 8:40 to 11:15 a.m.; afternoon session from 12:30 to 2:55 p.m.
- Bus Transportation Eligibility (Minimum Distance Requirements): High school, 2 miles; junior high schools, 1.5 miles; elementary schools, 1.25 miles; kindergarten through grade 3, 1 mile.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood School Board Rejects All Special Needs Busing Bids-August 21, 1980
With opening day just two weeks away, the Norwood School Committee voted 4-3 to reject all bids received the previous week for special needs student transportation. Acting under emergency procedures, the board announced it will call for new bids by Tuesday, with a potential contract award scheduled for Wednesday night. The rejected proposals came from…

-
Henry O. Peabody School Director Ruth Shea Ponders Retirement After 14 Years-August 12, 1980
After 14 years expanding vocational education, Henry O. Peabody School director Ruth Shea ponders retirement while securing a 97 percent graduate job placement rate.

-
Norwood School Administration Relocates to Willett School-July 24, 1980
The Norwood School Administration relocated to the George F. Willett School and enacted strict new graduation credit requirements.

-
Students to Face Stiffer Standards-July 18, 1990
In 1990 the town of Norwood was on the cusp of a significant change in its educational system. The school administration, led by Superintendent Louis J. Taris, had been studying ways to improve academic standards for over a year and a half. The result of this study was a proposal to double the number of…

-
Aaron Guild School Leased to Norwood CETA Consortium and EdCo for One Year-August 1, 1979
Norwood selectmen voted unanimously to lease the closed Aaron Guild School for one year to the Norwood CETA Consortium and the Educational Collaborative of Greater Boston (EdCo) for $148,000.

-
Norwood School Bus Billing Questioned-July 31, 1979
The Patriot Ledger’s July 31, 1979 edition brought to light a controversy surrounding the billing practices of Kiessling School Transportation of Dedham, which had been contracted by the town of Norwood to transport special needs children. The issue at hand was whether the company had overcharged the town for mileage on certain routes. According to…

-
School Department Releases Bus Routes and Eligibility Rules-August 30, 1978
As the late-summer excitement of a new academic year approached in 1978, the Norwood School Department officially released its comprehensive student transportation schedules, route mappings, and eligibility guidelines for the upcoming school term. Designed to ensure safe and orderly transit for thousands of local students, the announcement established clear boundaries and behavioral expectations for families…

-
Norwood School Committee Considers Staggered School Closing Plan-July 14, 1978
The school housing needs committee last night recommended a second school closing plan that would close the doors of the Callahan School in September, shut down the Balch School in 1981 and close a third, unnamed elementary school in 1983. The plan was backed by seven of the nine members voting and was billed as…

-
School Board Recall Urged-July 8, 1978
Discover the 1978 budget battle in Norwood, where deep cuts to the school district’s $11.3 million budget led to a controversial recall effort and a lawsuit involving the Massachusetts Teachers Association.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.