Contractors installing a new sprinkler system at Norwood High School assured the Permanent Building Committee last night that construction will be finished by next Friday, keeping the scheduled September 8 opening date on track.

Project Manager Robert Devoe of Boston’s ABC Sprinkler Co. stated that work will be 98 percent complete by Friday and announced he will personally oversee a second shift of workers starting Monday. The reassurance came after Assistant Superintendent James R. Donovan voiced concerns to the school committee on Wednesday night that installation delays might postpone the start of the academic year. Devoe noted that the cafeteria remains the only major area pending completion, after which the system will undergo rigorous pressure testing.

Engineering Friction and Gym Renovations

Committee members and contractors expressed frustration with Francis J. Thompson of HPR Services of New Hampshire, the engineer responsible for calculating the placement of over 800 sprinkler heads. Vice-Chairman Philip C. Swain reported that a minor calculation error by Thompson stalled necessary project approval from the Insurance Service Office (ISO). Committee members noted they had spent three weeks unsuccessfully trying to get Thompson to meet with the ISO, prompting a phone call and message left at his home during the meeting.

In other facility updates, Vincent Carlson—project manager for Korslund, LeNormand & Quann Inc. supervising high school renovations—reported that gym floor sanding is over 50 percent complete and expected to finish by Wednesday, allowing the application of the first of four finish coats and subsequent court line painting. While the gym floor will not be fully ready by the exact opening day of school, the building’s fire alarm system is scheduled for testing today. Carlson added that a temporary indicator panel has been installed at the insistence of the fire department until the permanent factory unit arrives, which will eventually tie in the completed sprinkler system.

Student Registration and Daily School Schedules

The school department announced registration and schedule guidelines for the upcoming 1976–77 academic year:

  • New Student Registration: Open for students entering the Norwood school system for the first time at all school administrative offices, Monday through Friday from 9:00 a.m. to noon and 1:00 to 3:00 p.m. Parents must provide birth and immunization certificates.
  • School Opening & Screening: All public schools open on September 8. Kindergarten screening runs from September 8 to 14, with kindergarten classes commencing September 15.
  • Daily Time Schedules:
    • High School & Henry O. Peabody School: 7:45 a.m. to approximately 2:30 p.m.
    • North & South Junior High Schools: 7:45 a.m. to 2:20 p.m.
    • Elementary Schools: 8:40 a.m. to 2:55 p.m.
    • Kindergarten: Morning session from 8:40 to 11:15 a.m.; afternoon session from 12:30 to 2:55 p.m.
  • Bus Transportation Eligibility (Minimum Distance Requirements): High school, 2 miles; junior high schools, 1.5 miles; elementary schools, 1.25 miles; kindergarten through grade 3, 1 mile.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

    Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.

  • Norwood Rejects Rockland Offer of Part Payment-July 16, 1985

    The summer of 1985 was a time of great economic uncertainty in Massachusetts, with the state facing significant budget deficits and high unemployment rates. However, amidst this backdrop of fiscal woes, the town of Norwood found itself embroiled in a dispute with its neighboring municipality, Rockland, over tuition fees for vocational school students. The issue…

    Stack of papers listing vocational school costs including tuition, equipment, registration, and book fees
  • Norwood High School Implements Total Smoking Ban-July 3, 1985

    In July 1985, the Norwood School Committee unanimously approved a total smoking ban at Norwood High School to begin in September, prioritizing the health of its students.

    Ashtray filled with cigarette butts labeled 'No Smoking' with people drinking and smoking in background
  • Rain-Damaged Cleveland and Prescott Schools Expected to Be Repaired by September-August 17, 1983

    Unexpected rainstorms caused roof leaks at the Cleveland and Prescott schools during active construction, though officials expect full contractor-funded repairs before the September opening.

  • School Long-Range Planning Panel to Deliver Progress Report-August 24, 1982

    Facing declining enrollments, Norwood’s school planning panel will deliver a progress report in October and final recommendations on grade configurations and potential school closures in January.

  • Norwood School Committee to Ask Teachers to Renegotiate Contracts-August 20, 1982

    Citing finance commission opposition and Proposition 2 1/2 limits, the school committee will ask teachers to renegotiate 8 percent pay raises or face town meeting review on September 20.

  • Norwood School Committee Narrows Superintendent Search to Three Finalists, Including Junior High North Principal James R. Savage-August 11, 1982

    Junior High North Principal James R. Savage was named one of three finalists for Norwood superintendent of schools, alongside Arlington assistant superintendent William J. Birmingham and Rhode Island administrator Nora M. Walker.

  • Peabody School Graduates Told Of Obligation To Support Education-June 25, 1982

    School officials emphasize community obligations and moral commitments to public education during exercises at Junior High School South.

  • Norwood School Committee Votes Eliminate Youth Hangout-July 31, 1981

    Following rampant vandalism, late-night drinking, and brush fires near Callahan Elementary School, the Norwood School Committee voted to fund a $6,000 clearing project to eliminate a notorious youth hangout.

  • School Committee Awards New Transportation Contracts-July 16, 1981

    After a difficult budget cycle in 1980, the committee avoided controversy by budgeting accurately and selecting trusted local transportation providers.


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.