Contractors installing a new sprinkler system at Norwood High School assured the Permanent Building Committee last night that construction will be finished by next Friday, keeping the scheduled September 8 opening date on track.
Project Manager Robert Devoe of Boston’s ABC Sprinkler Co. stated that work will be 98 percent complete by Friday and announced he will personally oversee a second shift of workers starting Monday. The reassurance came after Assistant Superintendent James R. Donovan voiced concerns to the school committee on Wednesday night that installation delays might postpone the start of the academic year. Devoe noted that the cafeteria remains the only major area pending completion, after which the system will undergo rigorous pressure testing.
Engineering Friction and Gym Renovations
Committee members and contractors expressed frustration with Francis J. Thompson of HPR Services of New Hampshire, the engineer responsible for calculating the placement of over 800 sprinkler heads. Vice-Chairman Philip C. Swain reported that a minor calculation error by Thompson stalled necessary project approval from the Insurance Service Office (ISO). Committee members noted they had spent three weeks unsuccessfully trying to get Thompson to meet with the ISO, prompting a phone call and message left at his home during the meeting.
In other facility updates, Vincent Carlson—project manager for Korslund, LeNormand & Quann Inc. supervising high school renovations—reported that gym floor sanding is over 50 percent complete and expected to finish by Wednesday, allowing the application of the first of four finish coats and subsequent court line painting. While the gym floor will not be fully ready by the exact opening day of school, the building’s fire alarm system is scheduled for testing today. Carlson added that a temporary indicator panel has been installed at the insistence of the fire department until the permanent factory unit arrives, which will eventually tie in the completed sprinkler system.
Student Registration and Daily School Schedules
The school department announced registration and schedule guidelines for the upcoming 1976–77 academic year:
- New Student Registration: Open for students entering the Norwood school system for the first time at all school administrative offices, Monday through Friday from 9:00 a.m. to noon and 1:00 to 3:00 p.m. Parents must provide birth and immunization certificates.
- School Opening & Screening: All public schools open on September 8. Kindergarten screening runs from September 8 to 14, with kindergarten classes commencing September 15.
- Daily Time Schedules:
- High School & Henry O. Peabody School: 7:45 a.m. to approximately 2:30 p.m.
- North & South Junior High Schools: 7:45 a.m. to 2:20 p.m.
- Elementary Schools: 8:40 a.m. to 2:55 p.m.
- Kindergarten: Morning session from 8:40 to 11:15 a.m.; afternoon session from 12:30 to 2:55 p.m.
- Bus Transportation Eligibility (Minimum Distance Requirements): High school, 2 miles; junior high schools, 1.5 miles; elementary schools, 1.25 miles; kindergarten through grade 3, 1 mile.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Junior High School Honor Rolls for the Last Term-This Day In Norwood History-July 21, 1997
Celebrating Academic Excellence at Norwood Junior High The academic landscape at Norwood Junior High School was highlighted by a formal recognition of student achievement, as the administration released the latest honor rolls for Grade 7 and Grade 6. These lists, comprised of students who attained HIGH HONORS and HONORS status, served as a public commendation…

-
Summer Education Program Helps Students Stay Sharp-August 12, 1992
Federal Chapter 1 funding revived Norwood’s summer remedial education program at the Cleveland School, combining academics with local field trips for 48 students.

-
Search for Superintendent Stirs Conflict on Committee-July 24, 1991
The Norwood School Committee engaged in a tense debate over expanding the superintendent search committee to include PTA representation and broader community voices.

-
Joseph Katchpole Succeeds George Usevich as Vice Principal of Norwood High School-August 23, 1990
Health and physical education department head Joseph Katchpole has been named acting vice principal of Norwood High School, succeeding George Usevich in the school administration.

-
Norwood to Sue Blue Hills School to Block Budget-July 19, 1990
The town of Norwood was on a collision course with the Blue Hills Regional Technical School in July 1990, as officials prepared to file a lawsuit to block the school’s revised budget for the upcoming academic year. The dispute had been brewing for several weeks, ever since the four district towns – Norwood, Holbrook, Dedham,…

-
$16,600 Grant Equips New Norwood High School Cable Television Studio-August 18, 1987
Norwood Community Television awarded a $16,600 grant to equip a new student-run television studio at Norwood High School, expanding local cable programming and production training.

-
Norwood High School Releases Fourth-Quarter Honor Roll-August 14, 1986
Norwood High School announced its student honor roll for the fourth quarter of the 1985-1986 academic year, recognizing academic achievement across senior, junior, and sophomore classes.

-
School Opening Delayed for High School Students-August 27, 1985
Norwood high school classes are delayed to September 9 as students temporarily relocate to Junior High North during a $5 million renovation project.

-
High School Students to Relocate to Vacant Junior High School North-August 21, 1985
Citing extensive construction delays by Anchor Construction Co., Norwood school officials voted to move nearly 950 high school students to Junior High School North for the start of the school year.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.