Rainwater leaked through the roofs of the Cleveland School and Prescott School last week while contractors were conducting active repairs, but town officials expect both buildings to be fully repaired and ready when schools open next month.
According to John P. Maleiko, supervisor of grounds and buildings, the water intrusion damaged roof insulation, ceiling tiles, and possibly floor tiles in a corridor of the Cleveland School, while ceiling tiles were slightly damaged at the Prescott School. Maleiko explained that the Ceasar Roofing Co. was replacing roofing material on the Cleveland and repairing gutters and roof edges at the Prescott when a sudden rainstorm hit. He noted that workers covered the exposed areas of the roofs with plastic, but the water got through anyway.
Maleiko, who was scheduled to report on the damage to the school committee that evening, confirmed that the Ceasar Roofing Co. will pay for all repair costs. He stated that the school department has made no estimate of the cost of the damage because it will not have to pay for the repairs. Furthermore, Maleiko said the firm assured him the damage would be repaired before schools open for the new academic year. (Reporting by local archives).
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Board Rejects Blue Hills Collaborative-July 29, 1976
The summer of 1976 was a time of great change and uncertainty for the town of Norwood, Massachusetts. As the nation celebrated its bicentennial, local residents were grappling with issues of education, finance, and community involvement. One such issue that dominated the headlines in July 1976 was the proposed Blue Hills Collaborative, a vocational school…

-
Norwood School Committee Approves Balch School Remedial Class and Eight-Period High School Day-July 31, 1975
The Norwood School Committee approved a pilot transitional first grade and modified kindergarten at Balch School to address kindergarten screening results and language needs.

-
School Committee Approves Shortened High School Day Format-July 16, 1975
The school committee of Norwood last night all but formally approved a switch to a shorter, eight-period day for the high school. The decision was made in response to a request from absent member Richard Joseph, who asked that the board defer its official vote on the plan until its next regular meeting in two…

-
Youth Enriched at Summer School-August 13, 1974
Directing over 600 local students, Norwood’s public summer school program completed its 30-day session, highlighting strong popularity for enrichment classes in arts and trades alongside vital remedial and special education tutoring.

-
Norwood School Committee Votes to Relocate School Administration Offices-August 1, 1974
The Norwood School Committee voted 5-2 to relocate central school administration offices to the Winslow School, pending cost estimates from Superintendent Philip O. Coakley.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974
After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.

-
Unfinished Junior High To Open On Schedule-July 8, 1974
Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.

-
School Board Rejects ‘Floating Principal’ Proposal-July 03, 1974
The Norwood School Committee held a contentious session on the evening of July 2, 1974, where, following two weeks of deliberation and a lengthy 90-minute executive session, the board voted 5-1 to reject a proposal to create a new administrative position titled “floating principal.“ The concept, initially championed by Committee Member Joseph M. Pentowski, was…

-
School Drop-In Centers Possible In Fall-June 24, 1974
Citing summer custodial constraints and a lack of air conditioning, town officials vote to survey local youths during the summer to prepare for a fall launch.

-
Norwood Sets $38 Tax Rate on Court-Ordered 100% Property Valuation for 1972-August 16, 1972
Announcing a 1972 tax rate of $38 per $1,000 under a court-ordered 100 percent property valuation, Assessor Chairman James J. Drummey concluded a major reassessment by Cole, Layer and Trumble.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.