Construction Committee Resolves Material Shortages

On July 26, 1974, The Patriot Ledger reported that the prospects for opening the new Junior High South on schedule looked increasingly promising following a progress update delivered at the Permanent Building Construction Committee meeting. Just two weeks prior, the targeted September 3 opening date appeared in jeopardy due to severe material shortages and delayed deliveries. However, architect James McGrath announced that a productive meeting with heating subcontractor Barber-Colman Co. of Canton successfully expedited the supply chain, ensuring that six vital temperature-control panels would be completed and shipped to the Endean Park site by August 15.

Architects from the Norwood firm Korslund, LeNormand and Quann, Inc. also consulted with state Department of Public Safety inspector A. Retacca to review the precise criteria required to secure a 90-day temporary occupancy permit—which can be extended for an additional 90 days—allowing students to begin classes on time and finally ending three years of double sessions necessitated by the tragic fire that destroyed the previous junior high facility.

Inspector A. Retacca stressed that student safety remains paramount, outlining mandatory conditions for partial occupancy. Proper ventilation systems, including operational exhaust fans, must be fully functional, and fire and vandal alarm systems must be tested and directly linked to local police and fire stations. Because an ongoing ironworkers’ strike threatened metal supplies, the inspector indicated that temporary wooden hand railings would be acceptable. While full completion of handicapped accessibility features might be waived if no disabled students are expected immediately or if accommodations can be managed on the ground level, the inspector requested a complete roster of any handicapped adults and children utilizing the building.

Furthermore, emergency generators, sprinkler systems, and fire chief sign-offs on carpet flammability reports are mandatory, and unfinished zones—such as the cafeteria, gymnasium, and industrial arts wing—must be strictly partitioned off from active classrooms. Encouraged by the progress report, the building committee also approved a base fencing bid of $33,781 from Reliable Fence Co. to secure the grounds, while reviewing ongoing work at the Aaron Guild Elementary School, where the board authorized a $4,772 payment to general contractor J.W. Praught Co. as construction moves toward a smooth fall opening.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Oldham School Drainage Repairs Scheduled For Completion-June 24, 1964

    Corrective Measures Target Long-Standing Controversy At Elementary Site Corrective measures designed to resolve persisting drainage problems at the Oldham Elementary School are scheduled to be completed by the end of this week. The ongoing drainage difficulties at the new school site had been the subject of a long controversy in discussions of the Oldham School…

  • School Study Committee Recommends 16-Room Elementary School-October 4, 1963

    The School Study Committee votes 5-4 to recommend a new 16-room elementary school and unanimously backs a Balch School addition for the upcoming special town meeting.

  • Oldham School Committee to Review Contractor Deadlines-September 12, 1964

    The Oldham School Committee meets to evaluate construction deadlines as Norwood public schools open for the academic year, while selectmen delay a store food license.

  • Oldham School Opening Set for Wednesday, New Teacher Appointments-August 30, 1963

    As Norwood prepares for the new academic year, the School Committee has announced plans to open the newly constructed John P. Oldham Elementary School next Wednesday, contingent upon final safety inspections of its heating and ventilating systems. While municipal electric light department crews rushed to finish electrical work and boilers were fired for the first…

  • Oldham Building Committee Demands Immediate Action Over Construction Delays and Poor Workmanship-August 20, 1963

    Citing roof leaks, unground floors, and poor workmanship, the Oldham School Building Committee confronted general contractor Edward Goverman and called in bonding company representatives.

  • School Building Committee Votes to Recommend Addition to Cleveland School-August 16, 1963

    By a 3-2 vote, Norwood’s Elementary School Building Committee recommended an eight-room addition to the Cleveland School rather than constructing a new facility on Wilson Street.

  • School Committee Considers New School Sites-March 22, 1962

    NORWOOD, Mar, 22 -Arthur B. Rodgers, chairman of the School Housing Study Committee which is responsible for the long-range projection of the towns future school needs, has requested information from the School Committee on its plans for new schools. Being considered by the School Committee are the possibilities of the construction of a second junior…

  • New Look at Norwood High School Addition-This Day in Norwood History-January 18, 1962

    NEW LOOK AT THE HILLTOP—The aerial camera of Larry McDavitt oí the Marguerite Studio embraces the entire expanded Norwood High School plant, now rapidly nearing completion. The addition, costing just under $2,000,000 and doubling the capacity of the old school, is now expected to be ready for occupancy February 15. It is planned to hold…

  • Pupils Get Three-Day Extension Due To High School Addition-September 7, 1961

    Pupils Get Three-Day Extension Due To High School Addition-This Day In Norwood History-September 7, 1961

  • Prescott School Dedication Plans Set-January 11, 1959

    Special Ceremonies Planned Week Apart Plans for the formal exercises marking the dedication of Norwood’s two new elementary schools – the Cleveland and the Prescott – were announced today by the committee. Arthur B. Rodgers, chairman of the Elementary Schools Building Committee, said that the dedication of the Prescot School located off Neponset and Dean…


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.