The Oldham School Committee is scheduled to hold a meeting on Monday night to formally evaluate whether the general contractor has successfully satisfied strict construction deadlines established for the completion of the new elementary school building.
Contractor Deadlines and School Readiness
The school committee previously instituted an August 21 cut-off date for completing all interior construction work, alongside a September 15 deadline for finishing exterior details. As of yet, the committee has not officially ruled on whether general contractor Melvin Goverman met the initial interior deadline, though a representative for the project’s architectural firm indicated that interior work was “pretty much” completed.
Despite the ongoing review of construction punch-list items for a building that originally opened late last winter, Superintendent of Schools Dr. Philip Coakley confirmed that the facility is completely prepared to welcome students for classroom instruction. Following a comprehensive on-site inspection of all Norwood public schools, Dr. Coakley reported that every building across town successfully completed summer refurbishing projects, leaving all facilities “completely operational” for today’s school openings.
Dr. Coakley emphasized that school administrators evaluated the Oldham facility primarily to ensure that essential safety and hygienic standards were fully satisfied, both of which passed inspection.
Board of Selectmen Delay License for Hills Department Store Food Counter
In municipal business, the Board of Selectmen voted to defer action on a Common Victualer’s license application submitted by Mrs. Mary H. Halligan of 14 Bright St. pending the receipt of a formal Board of Health report.
Mrs. Halligan appeared before the selectmen this week to outline her plans to operate a food counter at Hills Department Store, located within the Star Market Shopping Center on Nahatan Street. While the board noted that a favorable background report had already been returned by the Norwood Police Department, municipal regulations require a satisfactory Board of Health inspection and report prior to the final issuance of any commercial victualer license.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022
Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…

-
Norwood Adopts Whitman-Hanson School Prototype Model to Save Time and Money on New High School Construction-September 13, 2008
Norwood attempts to save time and money on its new high school construction project by reusing the architectural blueprints of Whitman-Hanson Regional High School.

-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985
Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.

-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985
Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.

-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976
Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.

-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974
Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.

-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974
After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.

-
Unfinished Junior High To Open On Schedule-July 8, 1974
Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.