Costly Road Connections and Projected Traffic Spikes Stall Neighborhood Plan
Soaring cost estimates and staggering traffic projections have convinced Norwood selectmen to abandon a proposed infrastructure fix designed to ease dangerous driving conditions for residents living in neighborhoods off Neponset Street.
Town Manager John J. Carroll reported to the board that connecting the Wedgewood and Norton Drive neighborhoods to the signalized traffic lights at Cherrywood Drive—providing motorists with a safer, light-controlled exit onto the busy roadway—would cost an estimated $130,000. The engineering breakdown revealed that connecting Longmeadow Road to Cherrywood over Old Farm Road would cost $80,000, with an additional $50,000 required to construct Old Farm from Longmeadow to Deerfield Road.
Finance Commissioner’s Appeal Meets Traffic Impact Data
The neighborhood traffic dilemma had been brought before selectmen by Thomas DiFrancia, a member of the Finance Commission and a resident of Norton Drive, who sought assistance for motorists struggling to navigate peak-hour traffic onto Neponset Street without the aid of a traffic light.
However, municipal traffic counts presented by Carroll demonstrated that opening the connection would trigger a massive influx of vehicles onto Cherrywood Drive:
- Morning Rush Hour: Exiting traffic would surge by 138 to 159 vehicles, building upon the baseline of just 21 vehicles—representing a 657 percent increase.
- Evening Rush Hour: Exiting traffic would jump by 60 to 69 vehicles, adding to the current nine-vehicle baseline—representing a 666 percent increase.
Faced with the prohibitive price tag and the dramatic neighborhood traffic surge, selectmen moved to drop the proposed roadway connection.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Guild School Recreation Center Project & Eliot Field Renovation-August 26, 1980

The Norwood Permanent Building Committee selected six architectural firms to interview for the Guild School renovation project, while Norwood Engineering secured the Eliot Field design contract.
-
Guild School Picked for Civic Center-July 8, 1980

Discover the 1980 decision that transformed the Aaron Guild School into a multi-purpose recreation hub, replacing the former Civic Center sold to Norwood Hospital.
-
Only Two Norwood Intersections Qualify for Right Turns on Red Under New State Law-October 3, 1979

Following a town survey, Town Manager John J. Carroll announces that right-on-red turns will be permitted at only two Norwood intersections when the state law takes effect.
-
Norwood Selectmen Consider One-Way Traffic, Business District Upgrades-August 8, 1979

Building on the Washington Street revitalization project, Town Manager John J. Carroll proposed working with local merchants to secure a second Urban Systems grant for Nahatan Street improvements.
-
Road Resurfacing Project in Norwood-This Day In Norwood History-July 21, 1978

Faced with decades of neglected road maintenance, Norwood officials debated an ambitious $1.9 million resurfacing plan in 1978. While proponents saw it as a path to smooth roads, others questioned the feasibility of the massive effort.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.