Reopening Target Set for Mid-November Following Construction Delays
Students attending the Henry O. Peabody vocational school may finally return to their classrooms by mid-November, according to estimates discussed at last night’s permanent building construction committee meeting. While project manager John Sosnowski of Anchor Construction of Lowell—the general contractor handling the $5 million renovation of the high school and the adjacent Peabody facility—maintained the building could be ready by November 8, committee members advised a more conservative timeline.
“Realistically, you’re not looking at anything earlier than Nov. 15, and probably Thanksgiving week,” stated committee member Roger Pelletier. Furthermore, architect Richard Heydecker of Korslund, LeNormand & Quann noted that a final post-construction cleanup will require an additional three to seven days.
The extensive renovation project was originally slated for completion on August 30. Because that deadline was missed, the school department had to scramble to find temporary alternative class spaces for the approximately 175 displaced Peabody students, scattering them between Junior High South and the Willett school—arrangements that both administrators and students have criticized as inadequate.
Permanent Building Committee Withholds $37,000 Over Defective Athletic Fields
In addition to delays at the vocational school, tensions flared regarding the high school renovation project. The construction committee voted to withhold approximately $37,000 in payments to Anchor Construction due to severe dissatisfaction with the newly redesigned football field and running track.
High School Athletic Director Arthur Gulla detailed a litany of complaints, pointing out that the field lacks proper grading and the necessary dome-topped curvature required for adequate drainage and turf protection, resulting in poor sod growth. Gulla warned that correcting the issues will cost two growing seasons. In the meantime, the school department is absorbing a $4,500 annual transportation expense to bus football players to Junior High South for practices, while playing all games entirely away from home.
“We’re spending $4,500 to transport kids to practice, and we probably will next year too,” Gulla said. “We’re playing all our games away—it’s not fair to the kids.” While Sosnowski defended the grading as correct, he agreed that a professional surveyor will evaluate the field the following week to determine whether regrading is necessary.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Superintendent Coakley Tells PTA Council That $4 Million in New School Construction Is Mandatory-September 10, 1965

Dr. Philip O. Coakley tells the PTA Council that $4 million in new school construction—including a new elementary and junior high—is mandatory to handle over-capacity enrollment.
-
Norwood School Committee Reviews Summer School Program and Proposes Token Fees-September 3, 1965

Following the successful completion of Norwood’s first town-sponsored summer school program—which enrolled approximately 330 local students in remedial coursework—the Norwood School Committee is evaluating future administrative structures, including a proposal to institute a nominal student fee. Superintendent Philip O. Coakley presented a comprehensive report detailing the inaugural summer session, noting that progress reports for every…
-
School Wiring Hazard Suspected at Norwood Junior High-September 3, 1965

Expressing deep concern over aging infrastructure, the Norwood School Committee has called for an immediate investigation into potential electrical wiring hazards at the Norwood Junior High School to determine whether emergency repairs are urgently required. The inquiry was initiated after Superintendent of Schools Philip O. Coakley delivered an alarming report on the condition of the…
-
Norwood Tennis Courts Recreation-July 10, 1965

On July 10, 1965, Norwood officials were actively working to resolve the placement of a proposed six-court tennis facility at the Prescott School. Recreation Superintendent Richard Ready noted that while the specific site remained undecided, he and other town officials were in the process of analyzing a location proposed by the Norwood School Committee. ⠀…
-
Town Meeting Approves Balch and Cleveland School Additions-October 23, 1964

Norwood voters overwhelmingly approved additions for the Balch and Cleveland schools during a town meeting session that also addressed Morrill Memorial Library plans and Plimpton Press electrical upgrades.
-
Norwood Renews Search For High School Principal-June 25, 1964

Officials plan to evaluate past candidates and request recommendations from Boston area colleges while Vice Principal John Mombouquette prepares for interim leadership.
-
Caroline Stratton Breaks Decades-Long Tradition as Female Freshman Class President-October 14, 1963

In a historic student election at Norwood Senior High School, Caroline Stratton becomes the first female freshman class president in over three decades.
-
Enrollment Hike Forces Split Classes in Norwood Public Schools-September 5, 1963

Norwood public schools experience an enrollment spike of 416 students, prompting split classes at Cleveland and Callahan schools and sparking a debate over elementary cafeteria capacity.
-
Eleventh-Hour Decision on Oldham School Registration-September 3, 1963

NORWOOD — An eleventh-hour session of the Oldham School Building Committee is being held tonight to make the decisive call on whether the newly constructed school will officially open its doors for student registration tomorrow morning. Final Scramble and Boiler Inspections Workmen labored through the weekend, including a full day on Saturday, trying to wrap…
-
Oldham School Opening Set for Wednesday, New Teacher Appointments-August 30, 1963

As Norwood prepares for the new academic year, the School Committee has announced plans to open the newly constructed John P. Oldham Elementary School next Wednesday, contingent upon final safety inspections of its heating and ventilating systems. While municipal electric light department crews rushed to finish electrical work and boilers were fired for the first…