The dashed line shows the University Ave extension.

State and local officials gathered on Friday for a ceremonial groundbreaking marking the official start of a $1 million highway project designed to spur commercial growth in Norwood’s largest industrial sector. Spearheaded by Town Manager John J. Carroll, the infrastructure initiative extends University Avenue to open up prime industrially zoned land, moving toward a long-term vision originally conceived back in 1966.

Two-Phase Highway Plan and Funding

The newly initiated project is divided into two distinct phases:

  • Phase I: Estimated at $1 million and contracted to the John Mahoney Construction Co. of Milton, this phase runs 3,850 feet west from the Canton project line to a dead-end just short of American Drive. It consists of two 12-foot travel lanes and is scheduled for completion by next June.
  • Phase II: Envisions connecting University Avenue directly to American Drive, alongside geometric and safety improvements to American Drive, Everett Street, and its intersection with Route 1. Town officials estimate this second phase is at least two years away from breaking ground.

Funding for the project is anchored by the federal Urban Systems program, covering 75 percent of the cost, while state funds pick up the remaining 25 percent. According to Town Manager Carroll, the town had originally saved $300,000 in state aid anticipating the road’s construction; when federal and state funding was secured last year, those reserved municipal funds were reallocated to repair other local roadways.

Local Dignitaries and State Officials in Attendance

Roughly 15 local and state figures participated in the groundbreaking ceremony, celebrating a project that state Department of Public Works Commissioner Sandino J. Tersigni noted was “a long time in coming.” State Highway Engineer Joseph Cronin—who oversaw five years of detailed planning, including environmental studies to protect local water wells—hailed the initiative as a valuable future bypass.

Local officials attending the event included Town Manager John J. Carroll (a former state DPW superintendent); Selectmen Walter J. Dempsey and Joseph F. Curran; Department of Public Works Superintendent Paul E. Wollenhaupt; Police Chief George J. DiBlasi; Fire Chief Thomas J. Barry Jr.; Finance Commission member Thomas DiFrancia; and Board of Assessors Chairman James J. Drummey.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood Kills Funds For School Addition-June 26, 1969

    Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

    Open ledger titled County Ledger 1969 with budget requests marked 'Budget Cut' and a judge's gavel on a wooden desk
  • Norwood Voters To Consider Lighting Funds-June 26, 1968

    The Finance Commission backs the utility expansion alongside a $163,000 sewer construction article, while the town master plan is deferred.

    Series of tall metal power transmission towers with electrical wires over fields and hills
  • Industrial Commission Welcomes Star Service Hub-June 30, 1967

    Following 50 intensive town meetings to resolve department regulations, developers project the new multi-million square foot industrial hub will lower Norwood’s local tax rate.

  • State Traffic Engineers Investigate Missing Stop Sign Reports in Norwood-August 31, 1966

    Local frustration over municipal traffic safety measures came to a head when town officials addressed long-standing delays regarding state approval for stop signs at key intersections. Commenting on the sluggish bureaucratic pace, one local selectman dryly remarked, “It takes an act of God to post a stop sign!” The exasperation stemmed from a nine-month delay…

  • Selectmen Call for Up-to-Date Delinquent Debt Listing-August 26, 1965

    Norwood selectmen called for updated listings of delinquent town service accounts and authorized Dr. Norton Fishman to construct an access road along George Willett Parkway at his own expense.

  • Oldham School Drainage Repairs Scheduled For Completion-June 24, 1964

    Corrective Measures Target Long-Standing Controversy At Elementary Site Corrective measures designed to resolve persisting drainage problems at the Oldham Elementary School are scheduled to be completed by the end of this week. The ongoing drainage difficulties at the new school site had been the subject of a long controversy in discussions of the Oldham School…

  • Parking Proposals in Norwood-July 31, 1963

    The Patriot Ledger’s July 31, 1963 edition brought forth a plethora of news stories that captivated the residents of Norwood and surrounding areas. Among these was the Parking Commission’s meeting with the Board of Selectmen to discuss proposals for acquiring land for parking purposes. This pivotal discussion took place in an executive session, which raised…

  • Winslow Train Station Abolished, Leading to Construction of Subway Hill-This Day In Norwood History- July 17, 1891

    This Day In Norwood History- July 17, 1891-Winslow Train Station Abolished, Leading to Construction of Subway Hill


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.