Special Town Meeting Voters Prepare to Weigh $2,995,000 Prospect Avenue Extension Junior High and $1,080,850 Elementary School in Early December
NORWOOD – Town voters were preparing to decide on a major $4,075,850 school construction package following architectural proposals unveiled by the Norwood Permanent Building Construction Committee for two new public school buildings. Reported in The Patriot Ledger on Monday, November 28, 1966, alongside architectural renderings of both proposed campuses, the building program featured a $2,995,000 junior high school planned for Prospect Avenue Extension and a $1,080,850 elementary school slated for Westover Parkway.
Designed to accommodate 1,000 pupils, the proposed Prospect Avenue Extension junior high school included plans for an auditorium, gymnasium, 30 standard classrooms, three science laboratories, and a cafeteria. Voters were scheduled to act on the junior high appropriation at a Special Town Meeting on December 5, 1966.
Meanwhile, the proposed $1,080,850 Westover Parkway elementary school was designed with 12 regular classrooms, two kindergarten rooms, two special education classrooms, four small-group instruction rooms, a library, and a cafeteria. Both school construction articles were slated to come before Town Meeting members during the special December sessions—with the elementary school vote scheduled for December 8, 1966—as Norwood worked to expand classroom capacity for its growing student population.
(Note: Multi-column newsprint OCR transpositions across page 9—where the two architectural photo captions for the proposed schools interleaved with the Catholic special education feature and the Norwood Hospital laundry expansion article—have been cleanly reassembled into standalone stories.)
Source: The Patriot Ledger • Monday, November 28, 1966 • Page 9
| Proposed 1966 Norwood School Project | 1966 Estimate | Est. 2026 Value |
|---|---|---|
| Prospect Avenue Extension Junior High School (1,000 Pupils) | $2,995,000 | $29,351,000 |
| Westover Parkway Elementary School | $1,080,850 | $10,592,330 |
| Combined Two-School Construction Package | $4,075,850 | $39,943,330 |
*Equivalent purchasing power based on U.S. Bureau of Labor Statistics CPI data.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…
-
Norwood Adopts Whitman-Hanson School Prototype Model to Save Time and Money on New High School Construction-September 13, 2008

Norwood attempts to save time and money on its new high school construction project by reusing the architectural blueprints of Whitman-Hanson Regional High School.
-
Norwood High School Renovation Plans Scrapped in Favor of New Building-October 15, 2005

Facing accreditation warnings and failing infrastructure, Norwood’s School Facility Task Force votes overwhelmingly to pursue a new high school building.
-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.
-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985

Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.
-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976

Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.
-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974

Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.