School Committee Reviews 1965 Teacher and Custodian Pay Scales as Voters Prepare for Special Ballot
NORWOOD – Members of the Westover Civic Association gathered on Tuesday night, November 17, 1964, in the Senior High School Auditorium to examine competing arguments surrounding the disputed $352,750 eight-classroom wing addition to the Cleveland Elementary School ahead of a townwide referendum scheduled for December 9. Reported in The Patriot Ledger on Wednesday, November 18, 1964, the forum gave residents an opportunity to hear directly from both supporters of the town meeting-approved expansion and advocates seeking to overturn it at the ballot box.
Speaking in favor of the referendum petition to overrule Town Meeting’s approval of the project, Dr. Norman Alpert urged Norwood residents to seek out and carefully weigh more detailed information than had thus far been provided before casting their votes. Conversely, David Adler, Ernest Paciorkowski, Richard Zahorsky, Mrs. Louise Maguire, and Miss Alice Polio (alongside Police Chief John Harrington) spoke in strong support of the eight-classroom addition, urging voters to uphold the project in order to address immediate elementary school space needs.
Meanwhile, the Norwood School Committee was scheduled to convene at 7:45 p.m. on Wednesday night, November 18, at school administration headquarters on Walpole Street to review proposed program allocations for the 1965 school budget—including substantial proposed salary increases for teachers and revised wage scales for school department custodians.
1964 Cleveland School Addition Cost Adjusted to 2026 Dollars & Site Legacy
Inflation-adjusted using U.S. Bureau of Labor Statistics CPI data ($1.00 in Nov. 1964 ≈ $10.42 in 2026)
| 1964 School Construction Project | 1964 Cost | 2026 Equivalent |
|---|---|---|
| Cleveland Elementary School 8-Classroom Wing Addition | $352,750 | ~$3,675,655 |
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…
-
Norwood Adopts Whitman-Hanson School Prototype Model to Save Time and Money on New High School Construction-September 13, 2008

Norwood attempts to save time and money on its new high school construction project by reusing the architectural blueprints of Whitman-Hanson Regional High School.
-
Norwood High School Renovation Plans Scrapped in Favor of New Building-October 15, 2005

Facing accreditation warnings and failing infrastructure, Norwood’s School Facility Task Force votes overwhelmingly to pursue a new high school building.
-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.
-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985

Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.
-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976

Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.
-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974

Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.