Despite ongoing construction challenges and labor disputes, the new Junior High South educational complex in Norwood remains on track for its scheduled September opening.
According to School Superintendent Dr. Philip O. Coakley, the “core” of the $4.5 million project—which includes the essential classrooms, administrative offices, and the auditorium—is expected to be fully operational in time for the start of the school year. Charles Worthington, the project’s clerk of the works, and Theodore J. Beaudet, the construction chief, confirmed that progress is sufficient to meet this goal. However, other portions of the facility, specifically the gymnasium, the cafeteria, and the industrial arts area, face a less certain timeline. Dr. Coakley indicated that he has yet to receive a definitive completion date for these auxiliary spaces from the general contractor, Rocheford Construction Co., Inc. of Natick.
The project, which saw its groundbreaking in October 1972 as a replacement for the aging Washington Street Junior High South, has been managed by the architects Korslund, LeNormand & Quann. John J. Egan, chairman of the Permanent Building Construction Committee, noted that while the project has experienced setbacks, it remains “well within the budget” originally established for construction. Addressing the delays, Dr. Coakley cited a previous carpenters’ strike as a primary factor, while Mr. Egan pointed to current labor strikes involving both painters and ironworkers as ongoing hurdles. Additional complications included the necessity of installing coil walls in the gymnasium, which delayed roof progress. Mr. Egan scheduled a follow-up committee meeting for the week of July 08, 1974, to conduct a more in-depth assessment of the construction schedule, which officially maintains a target completion date of September 1.
In addition to construction logistics, the committee is overseeing site improvements, including the installation of a fence along the rear of the school property situated at the corner of Washington and Mylod streets. The placement of this perimeter had been postponed due to revised plans submitted by the school board that incorporated a new running track into the field area. These specifications are currently awaiting final approval from the state School Building Assistance Bureau (SBAB). Furthermore, the committee has been forced to address damage caused by individuals driving vehicles onto the school’s playing fields, a recurring issue that necessitated the fencing plan. As the town nears the opening date, the Permanent Building Construction Committee continues to monitor the site closely to ensure the facility meets the needs of Norwood’s students.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Taxpayers Sue to Restore School Budget-July 6, 1978
Seeking to prevent a mid-summer school closure, 36 Norwood taxpayers filed a lawsuit in 1978 to restore $600,000 in education funding.

-
New Teachers Association President Richard T. King Focuses on Students and Educational Priorities Over Dollars-September 25, 1977
Newly elected Norwood Teachers Association President Richard T. King outlines a cooperative agenda focused on educational issues, special needs training under Chapter 766, and student scholarship programs.

-
Town Requests Bids for Audio-Activated Alarm System Trial at George F. Willett School-August 31, 1977
Seeking proactive solutions to combat recurring vandalism, the town manager’s office has officially requested bids for furnishing and installing an advanced audio-activated alarm system at the George F. Willett School on Westover Parkway. Trial Security System Specifications According to municipal procurement notices, sealed bids will be publicly opened at 11:00 a.m. on September 14 in…

-
Public Schools Announce 1977-78 Opening Schedules and Projected Enrollment of 5,842 Students-August 31, 1977
Superintendent of Schools Philip O. Coakley has officially announced that all Norwood public schools-covering grades 1 through 12, alongside special education classes-will open for the 1977–78 academic year on Wednesday, September 7. Registration is open daily in each school building from 9:00 a.m. to 3:00 p.m. ahead of opening day, with classrooms prepped for an…

-
Norwood Zeroes In On School Vandals-August 3, 1977
A newly formed blue‑ribbon security committee convened to confront a surge of costly vandalism at Norwood’s public schools. Members reviewed structural, technological, and community‑based deterrents while assigning formal research duties for a comprehensive townwide response.

-
Public Schools Enrollment Down 341 Students, Though Upcoming Apartment Construction Expected to Boost Numbers-September 16, 1976
Norwood school officials report a drop of 341 students in total enrollment, but anticipate new apartment construction will push numbers back up.

-
Louis Buscone Jr. Appointed High School Vice-Principal After Close School Committee Vote-September 9, 1976
Louis Buscone Jr. wins a one-year appointment as Norwood High School vice-principal by a 4-3 school committee vote as the board reviews declining enrollment figures.

-
Norwood School Committee Seeks Field Trip Funds and Awards Bus Transportation Contracts-July 29, 1976
Facing budget cuts that eliminated student field trips, the Norwood School Committee voted to appeal to the Finance Commission and special town meeting for restoration funds.

-
Norwood Board Rejects Blue Hills Collaborative-July 29, 1976
The summer of 1976 was a time of great change and uncertainty for the town of Norwood, Massachusetts. As the nation celebrated its bicentennial, local residents were grappling with issues of education, finance, and community involvement. One such issue that dominated the headlines in July 1976 was the proposed Blue Hills Collaborative, a vocational school…

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.