Despite ongoing construction challenges and labor disputes, the new Junior High South educational complex in Norwood remains on track for its scheduled September opening.
According to School Superintendent Dr. Philip O. Coakley, the “core” of the $4.5 million project—which includes the essential classrooms, administrative offices, and the auditorium—is expected to be fully operational in time for the start of the school year. Charles Worthington, the project’s clerk of the works, and Theodore J. Beaudet, the construction chief, confirmed that progress is sufficient to meet this goal. However, other portions of the facility, specifically the gymnasium, the cafeteria, and the industrial arts area, face a less certain timeline. Dr. Coakley indicated that he has yet to receive a definitive completion date for these auxiliary spaces from the general contractor, Rocheford Construction Co., Inc. of Natick.
The project, which saw its groundbreaking in October 1972 as a replacement for the aging Washington Street Junior High South, has been managed by the architects Korslund, LeNormand & Quann. John J. Egan, chairman of the Permanent Building Construction Committee, noted that while the project has experienced setbacks, it remains “well within the budget” originally established for construction. Addressing the delays, Dr. Coakley cited a previous carpenters’ strike as a primary factor, while Mr. Egan pointed to current labor strikes involving both painters and ironworkers as ongoing hurdles. Additional complications included the necessity of installing coil walls in the gymnasium, which delayed roof progress. Mr. Egan scheduled a follow-up committee meeting for the week of July 08, 1974, to conduct a more in-depth assessment of the construction schedule, which officially maintains a target completion date of September 1.
In addition to construction logistics, the committee is overseeing site improvements, including the installation of a fence along the rear of the school property situated at the corner of Washington and Mylod streets. The placement of this perimeter had been postponed due to revised plans submitted by the school board that incorporated a new running track into the field area. These specifications are currently awaiting final approval from the state School Building Assistance Bureau (SBAB). Furthermore, the committee has been forced to address damage caused by individuals driving vehicles onto the school’s playing fields, a recurring issue that necessitated the fencing plan. As the town nears the opening date, the Permanent Building Construction Committee continues to monitor the site closely to ensure the facility meets the needs of Norwood’s students.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Aaron Guild School Leased to Norwood CETA Consortium and EdCo for One Year-August 1, 1979

Norwood selectmen voted unanimously to lease the closed Aaron Guild School for one year to the Norwood CETA Consortium and the Educational Collaborative of Greater Boston (EdCo) for $148,000.
-
Norwood School Bus Billing Questioned-July 31, 1979

The Patriot Ledger’s July 31, 1979 edition brought to light a controversy surrounding the billing practices of Kiessling School Transportation of Dedham, which had been contracted by the town of Norwood to transport special needs children. The issue at hand was whether the company had overcharged the town for mileage on certain routes. According to…
-
School Supplies Budget Maintained at Prior Year Level Amid Spending Pressures and Utility Shortfall Concerns-September 14, 1978

Superintendent Louis J. Taris reports that Norwood’s school instructional supplies budget maintains prior-year per-pupil rates despite tight spending constraints.
-
School Department Releases Bus Routes and Eligibility Rules-August 30, 1978

As the late-summer excitement of a new academic year approached in 1978, the Norwood School Department officially released its comprehensive student transportation schedules, route mappings, and eligibility guidelines for the upcoming school term. Designed to ensure safe and orderly transit for thousands of local students, the announcement established clear boundaries and behavioral expectations for families…
-
Norwood School Committee Considers Staggered School Closing Plan-July 14, 1978

The school housing needs committee last night recommended a second school closing plan that would close the doors of the Callahan School in September, shut down the Balch School in 1981 and close a third, unnamed elementary school in 1983. The plan was backed by seven of the nine members voting and was billed as…
-
School Board Recall Urged-July 8, 1978

Discover the 1978 budget battle in Norwood, where deep cuts to the school district’s $11.3 million budget led to a controversial recall effort and a lawsuit involving the Massachusetts Teachers Association.
-
Taxpayers Sue to Restore School Budget-July 6, 1978

Seeking to prevent a mid-summer school closure, 36 Norwood taxpayers filed a lawsuit in 1978 to restore $600,000 in education funding.
-
Henry O. Peabody School Hosts Fifth Annual Harvest Fair and Flea Market-October 15, 1977

The Henry O. Peabody School for Girls holds its fifth annual Harvest Fair featuring food booths, crafts, flea market treasures, and student fundraiser activities.
-
Willett School PTA Launches Petition Drive to Fight Potential School Closure-October 11, 1977

Facing declining student enrollments across Norwood, the Willett School PTA initiates a petition drive to keep their school open, while school officials weigh options.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.