Contractors installing a new sprinkler system at Norwood High School assured the Permanent Building Committee last night that construction will be finished by next Friday, keeping the scheduled September 8 opening date on track.
Project Manager Robert Devoe of Boston’s ABC Sprinkler Co. stated that work will be 98 percent complete by Friday and announced he will personally oversee a second shift of workers starting Monday. The reassurance came after Assistant Superintendent James R. Donovan voiced concerns to the school committee on Wednesday night that installation delays might postpone the start of the academic year. Devoe noted that the cafeteria remains the only major area pending completion, after which the system will undergo rigorous pressure testing.
Engineering Friction and Gym Renovations
Committee members and contractors expressed frustration with Francis J. Thompson of HPR Services of New Hampshire, the engineer responsible for calculating the placement of over 800 sprinkler heads. Vice-Chairman Philip C. Swain reported that a minor calculation error by Thompson stalled necessary project approval from the Insurance Service Office (ISO). Committee members noted they had spent three weeks unsuccessfully trying to get Thompson to meet with the ISO, prompting a phone call and message left at his home during the meeting.
In other facility updates, Vincent Carlson—project manager for Korslund, LeNormand & Quann Inc. supervising high school renovations—reported that gym floor sanding is over 50 percent complete and expected to finish by Wednesday, allowing the application of the first of four finish coats and subsequent court line painting. While the gym floor will not be fully ready by the exact opening day of school, the building’s fire alarm system is scheduled for testing today. Carlson added that a temporary indicator panel has been installed at the insistence of the fire department until the permanent factory unit arrives, which will eventually tie in the completed sprinkler system.
Student Registration and Daily School Schedules
The school department announced registration and schedule guidelines for the upcoming 1976–77 academic year:
- New Student Registration: Open for students entering the Norwood school system for the first time at all school administrative offices, Monday through Friday from 9:00 a.m. to noon and 1:00 to 3:00 p.m. Parents must provide birth and immunization certificates.
- School Opening & Screening: All public schools open on September 8. Kindergarten screening runs from September 8 to 14, with kindergarten classes commencing September 15.
- Daily Time Schedules:
- High School & Henry O. Peabody School: 7:45 a.m. to approximately 2:30 p.m.
- North & South Junior High Schools: 7:45 a.m. to 2:20 p.m.
- Elementary Schools: 8:40 a.m. to 2:55 p.m.
- Kindergarten: Morning session from 8:40 to 11:15 a.m.; afternoon session from 12:30 to 2:55 p.m.
- Bus Transportation Eligibility (Minimum Distance Requirements): High school, 2 miles; junior high schools, 1.5 miles; elementary schools, 1.25 miles; kindergarten through grade 3, 1 mile.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Norwood Public School Students Score Strongly on State Basic-Skills Exams-September 2, 1982

Students across Norwood public schools have demonstrated exceptional academic performance, scoring remarkably well on state-mandated basic-skills tests for the second consecutive year. Released recently following examinations administered last spring, the district data reveals that only a very small handful of students across grades three, five, and eight failed to achieve minimum passing standards in reading,…
-
School Long-Range Planning Panel to Deliver Progress Report-August 24, 1982

Facing declining enrollments, Norwood’s school planning panel will deliver a progress report in October and final recommendations on grade configurations and potential school closures in January.
-
Norwood School Committee Narrows Superintendent Search to Three Finalists, Including Junior High North Principal James R. Savage-August 11, 1982

Junior High North Principal James R. Savage was named one of three finalists for Norwood superintendent of schools, alongside Arlington assistant superintendent William J. Birmingham and Rhode Island administrator Nora M. Walker.
-
Peabody School Graduates Told Of Obligation To Support Education-June 25, 1982

School officials emphasize community obligations and moral commitments to public education during exercises at Junior High School South.
-
Norwood High School 1962 Addition Cleared of Asbestos Hazards in State Safety Survey-November 3, 1981

Following state inspections of regional schools built between 1946 and 1972, Norwood High School has been cleared of asbestos hazards, with reinspection set for next year.
-
Junior High South Approves ‘Project Adventure’ Obstacle Course Gym Class-October 15, 1981

Junior High South introduces “Project Adventure,” an outdoor physical education obstacle course designed to build teamwork and move away from competitive sports.
-
Norwood High School Senior Edward J. Skricki Named Merit Scholarship Semi-Finalist; Three Peers Commended-October 13, 1981

Norwood High senior Edward J. Skricki achieves National Merit Scholarship semi-finalist standing, joined by commended classmates Judith Martowska, Susan O’Brien, and Joseph Petrie Jr.
-
Superintendent Taris Seeks to Curb Rising Costs of After-Hours School Building Use-September 4, 1981

Superintendent of Schools Louis J. Taris is pushing to rein in the surging volume of outside organizations utilizing school facilities during evening and weekend hours, citing mounting financial burdens on the school department. Dr. Taris informed the school committee that dozens of local organizations currently utilize school buildings after hours, frequently without paying any rental…
-
Norwood School Committee Votes Eliminate Youth Hangout-July 31, 1981

Following rampant vandalism, late-night drinking, and brush fires near Callahan Elementary School, the Norwood School Committee voted to fund a $6,000 clearing project to eliminate a notorious youth hangout.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.