Construction Committee Resolves Material Shortages

On July 26, 1974, The Patriot Ledger reported that the prospects for opening the new Junior High South on schedule looked increasingly promising following a progress update delivered at the Permanent Building Construction Committee meeting. Just two weeks prior, the targeted September 3 opening date appeared in jeopardy due to severe material shortages and delayed deliveries. However, architect James McGrath announced that a productive meeting with heating subcontractor Barber-Colman Co. of Canton successfully expedited the supply chain, ensuring that six vital temperature-control panels would be completed and shipped to the Endean Park site by August 15.
Architects from the Norwood firm Korslund, LeNormand and Quann, Inc. also consulted with state Department of Public Safety inspector A. Retacca to review the precise criteria required to secure a 90-day temporary occupancy permit—which can be extended for an additional 90 days—allowing students to begin classes on time and finally ending three years of double sessions necessitated by the tragic fire that destroyed the previous junior high facility.
Inspector A. Retacca stressed that student safety remains paramount, outlining mandatory conditions for partial occupancy. Proper ventilation systems, including operational exhaust fans, must be fully functional, and fire and vandal alarm systems must be tested and directly linked to local police and fire stations. Because an ongoing ironworkers’ strike threatened metal supplies, the inspector indicated that temporary wooden hand railings would be acceptable. While full completion of handicapped accessibility features might be waived if no disabled students are expected immediately or if accommodations can be managed on the ground level, the inspector requested a complete roster of any handicapped adults and children utilizing the building.
Furthermore, emergency generators, sprinkler systems, and fire chief sign-offs on carpet flammability reports are mandatory, and unfinished zones—such as the cafeteria, gymnasium, and industrial arts wing—must be strictly partitioned off from active classrooms. Encouraged by the progress report, the building committee also approved a base fencing bid of $33,781 from Reliable Fence Co. to secure the grounds, while reviewing ongoing work at the Aaron Guild Elementary School, where the board authorized a $4,772 payment to general contractor J.W. Praught Co. as construction moves toward a smooth fall opening.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Offer Made For Beacon School-This Day in Norwood History-October 22, 1942
Offer Made For Beacon School-This Day in Norwood History-October 22, 1942

-
Board Authorizes Borrowing For Peabody School-This Day in Norwood History-January 24, 1941
Joint Meeting Agrees To Go Forward With Project Construction of the Henry O. Peabody Trade School for Girls, to be in addition to the Norwood Senior High School, will soon be ready to go forward as it is reported that last Friday’s joint meeting of the selectmen, finance committee, school committee, and building committee for…

-
Judge Halloran Presents Norwood Plan For Peabody School For Girls At Hearing-This Day In Norwood History-November 19, 1938
Court Takes Under Advisement With Two Other Proposals Judge James A. Halloran presented the Norwood Plan for the H. O. Peabody School for girls on behalf of special town committee on the plan at the hearing held on Monday in Suffolk Probate Court. Two other plans, one from Simmons College, were presented for the court’s…

-
Closing of the Everett School Causes Overcrowding Emergency-November 3, 1923
Closing of the Everett School Causes Overcrowding Emergency-This Day In Norwood History-November 3, 1923

-
New Balch School Ready-This Day in Norwood History-September 2, 1913
SCHOOLS OF NORWOOD. New Balch Building to Open Tomorrow—Assignment of 12 New Teachers in Various Districts. NORWOOD, Sept 2—The public schools of Norwood open next Wednesday for the Fall term. This date is earlier than usual in this town. The work on the new Balch School Building has proceeded so far that the building is…

-
Norwood Votes For New Balch School, Buys Lots For Common & Town Hall Purposes-This Day In Norwood History-December 21, 1912
BUILDING TO COST $57,000. Norwood Votes to Have a 12-Room Building—Two Lots Purchased for a Public Park. NORWOOD. Dec 21—At a special town meeting last evening in Village Hall it was voted to build a 12-room schoolhouse in the Balch district, at a cost not to exceed $57,000. The sum of $150 was transferred from…

-
New Eight-Room Schoolhouse, Fire Station, Ordered-This Day In Norwood History-November 2, 1905
New Eight-Room Schoolhouse, Fire Station, Ordered This Day In Norwood History-November 2, 1905

-
The New North Schoolhouse-August 14, 1903
Rising proudly on Christian Hill, the new North Schoolhouse features 400,000 bricks laid by local contractors Spear & Smith and stands as a testament to Norwood labor and enterprise.

-
Back to School in 1899: Norwood’s Growing Classrooms
🎒 Back to School in 1899: Norwood’s Growing Classrooms As summer faded into crisp September mornings in 1899, the children of Norwood returned to school with slate boards in hand, stiff collars buttoned, and minds ready for learning. The town’s classrooms—modest yet ambitious—were undergoing a quiet transformation, reflecting broader shifts in American education at the…

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.