Citing a request from School Committee Chairman Charles C. Saraca, the permanent building committee voted last night to suspend planning for the proposed $6.1 million Norwood High School addition pending a comprehensive review of educational specifications.
Building committee chairman John J. Egan disclosed that he had received a letter from Saraca asking for a two-week suspension. Egan noted that the committee will revise its project brochure to provide a more detailed itemized cost breakdown for presentation at a contemplated November special town meeting. The original article was indefinitely postponed at the June session.
The $6.1 million project includes 43 additional classrooms, five new laboratories, seven seminar rooms, alterations, site preparation, and an estimated $327,000 Olympic-sized swimming pool for the 43-year-old facility. Egan warned that construction costs are climbing at a rate of 1 percent per month.
Additionally, the committee voted to consult Town Counsel Walter J. Gotovich regarding whether equipment and furnishings fall under state low-bidding statutes (Chapter 30, Section 39M). Committee member Justin C. Barton raised concerns that all items exceeding $2,000 may be legally required to go to the low bidder, a departure from past practice where furniture contracts were awarded independently.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Work Under Way At Junior High North-May 29, 1970
In 1970, Norwood Junior High North saw new fencing, repaving, and drainage improvements while a major school facilities survey moved toward completion, shaping long‑term planning.

-
Norwood Kills Funds For School Addition-June 26, 1969
Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

-
Strikes And Weather Delay North Junior High School Construction-June 17, 1969
Superintendent Warns Of Possible Double-Session Classes If Washington Street Facility Openings Fail A steel strike at the end of last summer halted installation of metal decking for the roof and delayed the roofer. Snow and freezing weather further hampered the project before the roof could be completed at the new school site. Without a roof,…

-
Parents Challenge Junior‑High Redistricting Plan-June 12, 1969
In June 1969, furious Cleveland School families took their grievances directly to town leaders, sparking a tense debate over school enrollment, modern facilities, and neighborhood identity.

-
School Building Committee Votes to Recommend Addition to Cleveland School-August 16, 1963
By a 3-2 vote, Norwood’s Elementary School Building Committee recommended an eight-room addition to the Cleveland School rather than constructing a new facility on Wilson Street.

-
School Committee Considers New School Sites-March 22, 1962
NORWOOD, Mar, 22 -Arthur B. Rodgers, chairman of the School Housing Study Committee which is responsible for the long-range projection of the towns future school needs, has requested information from the School Committee on its plans for new schools. Being considered by the School Committee are the possibilities of the construction of a second junior…

-
Redecorating Of School Interiors Is Recommended-February 9, 1950
Purchase Of Land For New Stands At High School Also Urged By Supt. Lynch Recommendations for the improvement of the present school plant before the town faced with the problem of new construction were advanced by School Superintendent Lincoln D. Lynch, as principal speaker at the February meeting of the Chamber of Commerce Tuesday night…