More than 1,500 junior high school students in Norwood will face double sessions this fall after the school board learned that the newly constructed Junior High School North will not be ready for occupancy until mid-November at the earliest.
Meeting in a unanimous vote, the school board authorized the temporary double-session arrangement at the old junior high facility after permanent building construction committee chairman John J. Egan reported that delivery and installation delays for essential equipment-such as shelving and science apparatus—will prevent a September 3 opening.
The disruption comes less than a year after the board voted to incorporate the ninth grade into the junior high configuration to alleviate severe overcrowding at Norwood High School. Egan and building committee member Richard Kief explained that once remaining equipment arrives, installation must proceed in a strict sequential order rather than concurrently. Kief noted that manpower shortages have compounded the timeline, though he praised general contractor C.R. Burns of Brookline for making every effort to push the project forward.
While kitchen and gymnasium equipment are ready, and roof leaks have been isolated away from the main instructional spaces, the school must secure a temporary occupancy permit from the state Department of Public Safety for the central “B” section-which contains a majority of the classrooms-to allow partial use while construction wraps up in other wings. Superintendent of Schools Philip O. Coakley acknowledged his earlier optimism, stating that everyone involved was deeply disappointed by the delay.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022
Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…

-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985
Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.

-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985
Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.

-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976
Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.

-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974
Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.

-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974
After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.

-
Unfinished Junior High To Open On Schedule-July 8, 1974
Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.