Architect Refuses to Accept 1,100 Square Feet of Exterior Tile at Special Meeting Addressing 22 Construction Issues

Several eleventh-hour construction and administrative hurdles were tackled by the Oldham School Building Committee during a special meeting called last night, headlined by a major dispute over defective masonry. Of prime importance among a list of 22 agenda items was a contentious problem involving the removal of roughly 1,100 square feet of exterior tile. Architect George H. Stoner advised the committee that he formally refused to accept the tile work, characterizing the installation as “poor workmanship.” Stoner explained that the root of the issue stemmed from the wall surface being improperly prepared before the tiles were laid, violating protocol since the tile firm was instructed never to proceed unless the foundation was in acceptable condition.
Prime contractor Edward Goverman Jr. of Canton stated he would be willing to tear down the flawed tiles himself, but noted that a professional tile setter would be required to redo the installation. However, union complications threatened to stall remediation; Goverman warned that because the original subcontractor was unionized, other union personnel currently working on the school might refuse to touch the repair job until all ongoing phases of construction are completed. Architect Stoner warned that the standoff could potentially trigger legal action between the prime contractor and the tile subcontractor, noting that he had requested industry experts to inspect the site. The Building Committee declined to dictate a solution to the contractor, demanding an immediate fix while expressing uncertainty over whether the extensive repairs could be wrapped up before the school’s September opening.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Schools Face Heating Oil Shortage for Upcoming Winter, While Band Camp and Library Art Programs Make Headlines-August 6, 1970
Superintendent Dr. Philip O. Coakley informed the Norwood School Committee that no companies submitted bids to supply 110,000 gallons of No. 5 heating oil for town schools due to quotas, shortages, and environmental regulations.

-
Bells Are Ringin’-July 3, 1970
The Norwood School Committee overhauled its student transportation system and faced an $8,000 wave of structural school vandalism in July 1970

-
Almost 50% of Graduates Head To College-July 10, 1969
The Norwood High School guidance department released a significant report on July 10, 1969, detailing the educational future of the school’s 419 graduates. The data revealed that approximately 45 percent of the class planned to attend four-year colleges that fall, a figure the department noted was likely the highest percentage of four-year institution acceptances in…

-
Special School Program Enters Fourth Year-June 24, 1969
Utilizing a low 5-1 student-to-teacher ratio, a staff of 36 professionals works to reinforce reading skills and improve academic performance for public and parochial school children.

-
School District Prepares for New Academic Year with Orientation Institute and Registration Dates-August 14, 1968
Superintendent Dr. Philip O. Coakley announced student registration dates and school opening schedules as Norwood public schools welcome dozens of new educators for the 1968-1969 academic year.

-
Alan R. Wonson Reappointed as Principal of Winslow Elementary School-August 31, 1967
Following an executive session, Committee Chairman Francis X. Sheehan Jr. announced that the Norwood School Committee has reappointed Alan R. Wonson of Westwood as principal of the Winslow Elementary School, effective immediately. Wonson, the former vice-principal at the Cleveland Elementary School, had previously been appointed by a unanimous committee vote earlier in the month; however,…

-
School Committee Discloses Closed-Session Debate Over Elementary School Principalship Merger-August 25, 1967
School committee minutes revealed a shelved plan to merge Shattuck and Winslow schools

-
School Committee Considers Sweeping Administrative Reorganization Plan-August 24, 1967
School Committee Chairman Francis X. Sheehan Jr. proposed a sweeping administrative reorganization creating an associate superintendent to streamline Norwood school management

-
Schools Prepare for 5th Annual New Teacher Orientation-August 22, 1967
Superintendent Dr. Philip O. Coakley welcomed 58 incoming educators at the fifth annual teacher orientation institute at Prescott School, introducing new faculty across secondary and elementary schools.

-
Norwood Teachers Association Submits $1,000 Pay Increase Proposal-August 18, 1966
The Norwood Teachers Association submitted a $1,000-plus pay raise proposal as the school committee signed its first collective bargaining agreement amid debate led by John J. Cavanaugh and William Egan.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.









