Architect Refuses to Accept 1,100 Square Feet of Exterior Tile at Special Meeting Addressing 22 Construction Issues

Several eleventh-hour construction and administrative hurdles were tackled by the Oldham School Building Committee during a special meeting called last night, headlined by a major dispute over defective masonry. Of prime importance among a list of 22 agenda items was a contentious problem involving the removal of roughly 1,100 square feet of exterior tile. Architect George H. Stoner advised the committee that he formally refused to accept the tile work, characterizing the installation as “poor workmanship.” Stoner explained that the root of the issue stemmed from the wall surface being improperly prepared before the tiles were laid, violating protocol since the tile firm was instructed never to proceed unless the foundation was in acceptable condition.

Prime contractor Edward Goverman Jr. of Canton stated he would be willing to tear down the flawed tiles himself, but noted that a professional tile setter would be required to redo the installation. However, union complications threatened to stall remediation; Goverman warned that because the original subcontractor was unionized, other union personnel currently working on the school might refuse to touch the repair job until all ongoing phases of construction are completed. Architect Stoner warned that the standoff could potentially trigger legal action between the prime contractor and the tile subcontractor, noting that he had requested industry experts to inspect the site. The Building Committee declined to dictate a solution to the contractor, demanding an immediate fix while expressing uncertainty over whether the extensive repairs could be wrapped up before the school’s September opening.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Youth Enriched at Summer School-August 13, 1974

    Directing over 600 local students, Norwood’s public summer school program completed its 30-day session, highlighting strong popularity for enrichment classes in arts and trades alongside vital remedial and special education tutoring.

  • Norwood School Committee Votes to Relocate School Administration Offices-August 1, 1974

    The Norwood School Committee voted 5-2 to relocate central school administration offices to the Winslow School, pending cost estimates from Superintendent Philip O. Coakley.

  • Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

    After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.

  • Unfinished Junior High To Open On Schedule-July 8, 1974

    Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.

  • School Board Rejects ‘Floating Principal’ Proposal-July 03, 1974

    The Norwood School Committee held a contentious session on the evening of July 2, 1974, where, following two weeks of deliberation and a lengthy 90-minute executive session, the board voted 5-1 to reject a proposal to create a new administrative position titled “floating principal.“ The concept, initially championed by Committee Member Joseph M. Pentowski, was…

    Silhouettes of students running through shattered walls with arrows labeled growth, population, overcrowding, and expansion in a school-themed comic style
  • School Drop-In Centers Possible In Fall-June 24, 1974

    Citing summer custodial constraints and a lack of air conditioning, town officials vote to survey local youths during the summer to prepare for a fall launch.

    School hallway with blue lockers, wooden floor, sunlight streaming through large windows, and signs for art wing
  • Public Schools Face Delays and Possible State Action on Mandatory Hot Lunch Program-August 31, 1973

    Parents of elementary school students in Norwood will need to continue packing brown-bag lunches for the start of the academic year. School Superintendent Philip O. Coakley announced that the town will fail to meet the state-mandated September deadline for implementing a universal public school hot lunch program, exposing the municipality to potential legal action by…

  • School Board Reverses Vote, Keeps NorWest Woods Pupils at Oldham-August 29, 1972

    In a reversal of a previous decision, the School Committee has voted to keep 46 elementary school children from the Nor-West Woods apartment complex at the Oldham School, rescinding a July 5 vote that would have transferred them to the Shattuck School. Superintendent Dr. Philip O. Coakley explained that the committee revoted on the matter…

  • Norwood Sets $38 Tax Rate on Court-Ordered 100% Property Valuation for 1972-August 16, 1972

    Announcing a 1972 tax rate of $38 per $1,000 under a court-ordered 100 percent property valuation, Assessor Chairman James J. Drummey concluded a major reassessment by Cole, Layer and Trumble.

  • Junior High Alternate Estimates Sought-June 25, 1971

    A sharp debate divides Town Manager Walter Blasenak and finance officials over mounting unappropriated architectural fees for Boston design firms.


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.